1 / 15

Linac Design and Status P. Emma LCLS DOE Review SC1/SC2 Breakout February 8, 2006

Linac Design and Status P. Emma LCLS DOE Review SC1/SC2 Breakout February 8, 2006. LCLS. Outline. Linac intro. & parameters Low-charge operation Project documentation Commissioning plans Inj-BC1 commissioning Trajectory jitter & tolerances Summary. Commission in Jan. 2008.

kcaroll
Télécharger la présentation

Linac Design and Status P. Emma LCLS DOE Review SC1/SC2 Breakout February 8, 2006

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Linac Design and StatusP. EmmaLCLS DOE ReviewSC1/SC2 BreakoutFebruary 8, 2006 LCLS

  2. Outline • Linac intro. & parameters • Low-charge operation • Project documentation • Commissioning plans • Inj-BC1 commissioning • Trajectory jitter & tolerances • Summary

  3. Commission in Jan. 2008 Commission in Jan. 2007 LCLS Accelerator and Compressor Schematic 250 MeV z  0.19 mm   1.6 % 4.30 GeV z  0.022 mm   0.71 % 13.6 GeV z  0.022 mm   0.01 % 6 MeV z  0.83 mm   0.05 % 135 MeV z  0.83 mm   0.10 % Linac-X L =0.6 m rf= -160 Linac-0 L =6 m rf gun L0-a,b Linac-3 L 550 m rf  0° Linac-1 L 9 m rf  -25° Linac-2 L 330 m rf  -41° 25-1a 30-8c 21-3b 24-6d ...existing linac 21-1 b,c,d undulator L =130 m X BC1 L 6 m R56 -39 mm BC2 L 22 m R56 -25 mm DL1 L 12 m R56 0 DL2 L =275 m R56  0 SLAC linac tunnel research yard

  4. Low-Charge Option (200 pC) Charge: 1 nC0.2 nC Slice emittance: 1 mm0.8 mm Gun Current: 10030 A (10 ps6.5 ps) Final current:3.4 kA2.0 kA(same Lsat) und. wakes • BC2 CSR De 1/5 • L2 trans. wake De1/16 • Peak current jitter  1/2 • X-ray pulse 85 fs (was 200 fs) • ‘No’ undulatorwakes • PFEL 10 GW, 1012 photons • eng. baseline unchanged • 1-nC still fully supported • Full Elegant and Ginger/Genesis S2E’s completed 1 nC 0.2 nC

  5. Project Documentation • Physics Requirements Documents (PRD) • Engineering Requirements Documents (ESD) 31 PRD’s & ESD’s 104 magnet sheets http://www-ssrl.slac.stanford.edu/lcls/internals/documents/prd/ http://www-ssrl.slac.stanford.edu/lcls/linac/specs/

  6. Example PRD’s 1.1-006, Magnets 1.1-008, Vibrations 1.1-010, Polarities 1.3-017, Collimators

  7. Machine Commissioning Plans • Work in MS-Project • One file/manager per system • Link to milestones and events in Master file Injector-BC1 BC2 LTU-und. install install Dec. ‘05 Sep. ‘07 Dec. ‘07 Mar. ‘08 Dec. ‘06 Aug. ‘06

  8. Linac Commissioning Plans

  9. Injector Through BC1 Commissioning no laser-heater sE gex,y and slice RF deflector E

  10. Injector Through BC1 Commissioning (2) CSR relative bunch length monitor? BC1 sE stopper X-band RF gex,y E slice gey

  11. Trajectory Stability – Sources of Jitter(f > 10 Hz; Use feedback for f < 10 Hz) • Steering coil current regulation (121 x, 121 y) • Bend magnet trim coil current reg. (13 x, 2 y) • Misaligned quads/sol’s + current reg. (148 mag’s) • Quad/solenoid mech. vibration (148 mag’s) • CSR kicks with bunch length jitter (BC2, x only) • Transverse wakes and charge jitter (X-band RF) • Drive laser pointing stability Expected Sources of Transverse Jitter

  12. Quadrupole Magnet Vibration Existing Linac ‘QE’ Quadrupole Magnets R. Stege, J. Turner, 1994 rubber boot on water pump • 12 quads need rms 500 nm (most new injector quads) • 101 magnets need rms 100 nm (existing linac quads) • 35 quads need rms 50 nm (mostly new LTU quads)

  13. CSR-Induced x-Trajectory Jitter 10% bunch length jitter  16% ‘core’ trajectory jitter 1-nC 22 mm 20 mm 18 mm core

  14. Trajectory Stability – Tol’s & Expectations System Stability Requirements at f > 10 Hz • Steering coils (30-100 ppM  6% of beam size) • Trim coils (30-100 ppM  2%) • Misaligned quads (Dx 200 mm: 25-100 ppM  6%) • Quad/solenoid vibration (0.05-1 mm required  10%) • CSR kicks (1 nC, Dsz/sz  10%:  ~20%, x-only) • Wakes (Dx 200 mm, DN/N  2%  2%) • Drive laser pointing ( 3%) 0.2 nC is more stable

  15. Summary • Linac parameters are well defined and stable • Project documents describe requirements • Detailed commissioning plans exist and are being further advanced • Studies finished on collimation, machine tune-up, and expected trajectory stability • Longitudinal feedback needed (see J. Wu) • Linac through BC1 is ready for construction in Fall ’06 and commissioning in Dec. ’06.

More Related