PSB beam dump replacement project status

PSB beam dump replacement project status. PSB LS1 coordination meeting Alba Sarri ó 04 -Dec-2013. Work planning. Preparation of the area: dismantling of beam line equipment (BT, BTY, BTM ) → 15/07/13 – 02/08/13

leoma
Télécharger la présentation

PSB beam dump replacement project status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PSB beam dump replacement project status PSB LS1 coordination meeting Alba Sarrió 04-Dec-2013

  2. Work planning • Preparation of the area: dismantling of beam line equipment (BT, BTY, BTM) → 15/07/13 – 02/08/13 • Disposal operations of existing dump and its shielding: dismantling and storage in ISR → 05/08/13 – 29/08/13 • Cleaning and decontamination of cavity → 30/08/13 – 19/09/13 • Installation of new beam dump and its shielding → 30/09/13 – 08/10/13 • Re-assembly of BTM beam line equipment → 21/10/13 – 01/11/13 • Installation of BTY-QFO108 new support → 26/11/13

  3. Tasks to be done • Re-assembly BTY line elements: • Adjustments in BTY-QFO108 new support: drilling holes, attach black plate (magnet support): 04/12/13 • Installation BTY magnets (BTY-QFO108 and BTY-QDE104) and stopper: 04/12/13 – 05/12/13 • Installation vacuum pipes in BTY line • Survey BTY line • Painting floor and walls

  4. Tasks to be done • Re-assembly BTY line elements: • Installation cooling system: foreseen for 02/12/13 – 13/12/13, delayed until January, no confirmed date yet. • Re-assembly stairs: a modification is also needed, no design provided yet. • Re-assembly cable rack • Re-assembly cupboard

  5. Tasks to be done

  6. Planning: tasks to be completed

  7. Thanks for your attention