1 / 17

Construction Site Erosion and Sediment Controls

Construction Site Erosion and Sediment Controls. Section 6. Maintenance and Inspection. Maintenance. Two categories of maintenance activities: Repair and replacement of erosion control devices Removal and disposal of sediment from the devices. Maintenance Trigger Points.

liam
Télécharger la présentation

Construction Site Erosion and Sediment Controls

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Construction Site Erosion and Sediment Controls Section 6. Maintenance and Inspection

  2. Maintenance Two categories of maintenance activities: • Repair and replacement of erosion control devices • Removal and disposal of sediment from the devices

  3. Maintenance Trigger Points • Remove sediment from basins and ditch checks when 1/2 full • Remove sediment from silt fence when 1/3 full • Other trigger points may be specified by the Engineer (see Section 621.03 (l) of the Specifications)

  4. Maintenance Trigger Points Sediment is too high behind this baled straw ditch check; maintenance is needed to prevent water from continuing to flow around check

  5. Sediment Removal and Disposal • Sediment removed shall be deposited and stabilized as described in Sections 110 and 201 or as directed by the Engineer • In some cases sediment controls may be allowed to “silt in” and never be removed or cleaned out

  6. Winterizing • A pre-winterizing meeting will be scheduled with the Contractor to determine what is needed before shutting down for the winter • Plans should be made to maintain erosion and sediment control while work is shut down

  7. Inspection Duties • Be familiar with Plans and Specifications • Be familiar with SWPPP • Check SWPPP for errors and problems prior to start of construction • Discuss details of SWPPP with Contractor’s personnel at Pre-construction Conference

  8. Inspection Duties • Ensure that all BMPs are installed in accordance with the Plans and Specifications • Ensure compliance with Section 110 of Specifications • Ensure that wash water from concrete trucks is disposed of properly • Conduct SWPPP inspections and document status of BMPs as well as any instructions to Contractor

  9. SWPPP Inspection Reports • Completed a minimum of every 7 days and within 24 hours of any ½-inch rainfall • Copy should be sent to Contractor as soon as possible for corrective actions • Document Contractor compliance in job diary • Once the RE has received a copy of the NOT, reports may cease for the project

  10. Construction Wastes • Section 110.07 of the Specifications describes the Contractor’s responsibilities for pollution prevention • Inspect Contractor’s materials, stockpiles, and other pollutant sources on the R/W and make sure they are properly safeguarded • Inspect Contractor’s housekeeping procedures

  11. SWPPP Inspection Reports Critical points for inspection: all disturbed areas of the site, erosion and sediment BMPs, vehicle entrances and exits, and, material storage areas

  12. SWPPP Inspection Reports

  13. SWPPP Inspection Reports

  14. Documentation Requirements • NOI must be filed with ADEQ, the Central Office will include the NOI in the Contract • Copy of all Change Orders regarding the SWPPP must be on file • Copy of the Pre-construction Conference minutes regarding discussions of the SWPPP must be on file

  15. Documentation Requirements • Public Notice must be posted on bulletin board • Copy of all documentation regarding SWPPP should be kept in the RE’s Office and shall be readily available to all State and Federal inspectors • When deficiencies are noted in the SWPPP report, a copy must be given to the Contractor

  16. Final Stabilization • Final stabilization as defined by Federal regulation is achieved when a uniform perennial vegetative cover of at least 70% of the native background cover for the area has been established • Notice of Termination (NOT) is submitted once final stabilization is established

  17. Questions?