SCT Production Status

SCT Production Status. ‘Snap-shot’ of the status of the SCT production (May 2003) Barrel Modules Barrel Opto-harnesses Barrel support structures & cooling Endcap Modules Endcap Opto-harnesses Endcap support structures & cooling Power & Cables Off-detector readout Assembly & Integration.

lovie
Télécharger la présentation

SCT Production Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SCT Production Status ‘Snap-shot’ of the status of the SCT production (May 2003) • Barrel Modules • Barrel Opto-harnesses • Barrel support structures & cooling • Endcap Modules • Endcap Opto-harnesses • Endcap support structures & cooling • Power & Cables • Off-detector readout • Assembly & Integration

  2. Barrel Modules • Modules • Barrel module PRR May 01 • Detector production May 03 ( I.e. complete) • Hybrids target end date Aug 03 1214/2500 (49%) • Baseboards target end date Oct 03 1481/2530 (59%) • Modules-Japan 356/ 786 (45%) • Modules-UK 79/ 549 (14%) • Modules-US 48/ 483 (10%) • Modules-Scand (qualification soon) 16/ 404 ( • Total (2112+5%) 499/ 2218 (22%) • Modules target end date Apr 04

  3. Barrel Optoharnesses • Opto-harnesses • Production now underway after slow start-up • Main problem was ESD damage to DORIC ASIC • First 2 harnesses fully evaluated • Schedule can be recovered • B3 Jun 03 • B6 Jul 03 • B5 Sep 03 • B4 Oct 03

  4. Barrel Structure & Cooling Support structures • All 4 CF cylinders delivered • …but there are ~40000 small parts! Cooling • Design is finalised • Production of cooling circuits underway • On critical path

  5. Endcap Modules • Modules • Endcap module PRR Aug 02 & Nov 02 • Hybrid design was validated as suitable for production • Hybrid production & assembly transferred to industry • Thermal performance validated • Production • Hybrids • Pre-series of 200 in production – some delivered • Full order for 2500 placed • Spines • 200 in production by Protvino/MPI • Contract in place for 2500 • Module assembly • All 3 clusters have started ‘qualification’ process • 1rst modules within specification • Aim is to have all sites qualified in 2 months • Goal is to complete module production in Sep 04 • Very ambitious – will require extra resources

  6. Endcap Optoharnesses, Structure & Cooling • Opto-harnesses • Simpler as the electronics is incorporated in the hybrid • Production can start as soon as fibre lengths finalised • Cooling • Design is finalised & prototyped • Production of cooling circuits ready to start • Support structures • CF disks & support cylinders ordered • First 4 delivered; complete by Dec 03 • Again many small parts • 4 first disks & Stub cylinder delivered • Expect delivery of cylinders by Aug 03 • Disk PAR MAY 19 • Critical issue is to complete disc machining by July

  7. SCT Power, Cables, Readout, Assembly & Integration • Power & Cables • System designed & all elements prototyped • FDR/PRR scheduled for May 28 • Early production necessary for macro-assembly • Cable tender in June • Readout • System designed & all elements prototyped • FDR/PRR May 13 • Early production necessary for macro-assembly • Assembly & Integration • B3 is at RAL to be equipped with services • B3 will go to Oxford to have modules added Jul 03 – Nov 03 • SR building at CERN now available • Program of work underway to commission cooling, power & readout