1 / 6

Cathode Production Status

Cathode Production Status. Muon Week April10th 2003. A. Benvenuti. INFN Bologna. Ordered last October. Delivered. Ready for Shipping. Tape Shipment arrived at Custom House (only one more foreseen)

umed
Télécharger la présentation

Cathode Production Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cathode Production Status Muon Week April10th 2003 A. Benvenuti INFN Bologna

  2. Ordered last October Delivered Ready for Shipping Tape Shipment arrived at Custom House (only one more foreseen) Disposables (Spacers, protective bags, shoe covers, brushes, blades….) cleared through Customs (Last shipment) Inventory of rejected items, spares needed is becoming crucial

  3. Planned Shipments up to Spring 2004 Chimney One Shipment = 12 boxes with 943 Cathodes Shipment 9 Ready for loading; Shipment 10: 1 MB1 and 5 Phi Boxes ready on 08/04/03 187 732 Required + Spares

  4. Almost finished by Spring of 2004

  5. Keep Updated • Cathode production should be completed well ahead of the chambers: • Cathode should be stored in a cool area • Use early boxes first. Protective bags not used before February 2002 • Do not leave cathodes exposed to air for a long time, they attract smog use protective plastic film if they are stored outside bags. • Use Monocathodes, they cost as much as regular ones and they are counted in the total • Once cathode production is stopped, the assembly site must be cleared. • Must plan for cathode requirements beyond foreseeable spares

  6. Cathodes Required for the Entire DT Construction ( with 19 Spares) MB4/8,12 produced in Legnaro Grand Total = 187 732 cathodes