An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ARA Production Status Jiwoo Nam

  2. Overall • Still Procurement Stage • Mechanics under fabrication • Delay on DAQ-stack boards, UW/UMD

  3. DAQ Box • Mechanical Structure: Under fabrication, Due 1-2 weeks • DAQ-board stacks: (Problematic!) ATRI Board will be ready in a week All PCBs to be sent to OSU with ATRI boards • Cables / connectors:RF Connectors: A restricted bidding to be started ASAP, waiting accounting procedures (short delivery time < 1 week): Cables: RF cables ready, Power cables will be ready by 1-2 weeks • Filters: Waiting for shipping from UW in 2 weeks All others ready or under purchasing process smoothly

  4. Antennas • V-pol production Splitting to three companies by parts to avoid bidding (Wire + Ring + PC tube/Assembly)  Should be ready by End of Aug • H-pol production Endcap plate (on going 1-2 weeks) Waiting for PC tube from UW Ferrites to be ready by Mid-Late Aug Antenna Cables to be ordered!

  5. LNA Box • Housing 4 sample productions from different companies  Will choose one of them today. 3 weeks lead time and partial delivery would be available  Assembly will be started with spare parts

  6. Optical Modules (TX/RX) Waiting housing and parts from UW (Schedule TBC)

  7. Cables Down Hole RF cables including 200 m power have been ordered (Middle - End of Aug) RF Jumpers for Antenna should be ordered ASAP

  8. Storage/Carriers • Antennas/Optical Modules: Customized Foam • LNA Box Water proof Pelican Box • DAQ Box / Cables To be placed into wooden crates with foams • Cables Use delivered creates/boxes?

  9. Manpower • NTU Jiwoo, Tsungche, Chiching, Chuanjui, Lice, two undergraduates • OSU (Aug 07~20) Eugene and Paul • Chiba (Schedule TBD) Aya, Keiichi • UH (Schedule TBD) Brendan or Ben • UW (Schedule TBC) Mike & Albrecht (short visit around Aug 21) • Missing Test Crews: Patrick & one from UCL

  10. Work Environment • Two Work Tables Ready (total 4) • A soldering bench table ready (total 2) • Part Drawer Racks Ready (2x2) • Cable Racks to be produced