1 / 72

Robin Lafever LBNL and LNGS

CUORE Clean room Radon abatement Several scenarios exploring the ‘Radon Box’ approach This is an unfinished DRAFT, slammed together for today’s phone meeting !. Robin Lafever LBNL and LNGS. Scenario 1 The generic ‘Radon Box’.

meara
Télécharger la présentation

Robin Lafever LBNL and LNGS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CUORE Clean room Radon abatementSeveral scenarios exploring the ‘Radon Box’ approachThis is an unfinished DRAFT, slammed together for today’s phone meeting ! Robin Lafever LBNL and LNGS

  2. Scenario 1 The generic ‘Radon Box’ The primary intent for this presentation is to summarize ongoing discussions of the CUORE clean room design with enough detail to give clean room vendors an overview of our requirements. Since Radon abatement is NOT a part of typical clean room construction, this presentation hopefully provides a starting point to evaluate the feasibility and practicality of implementing an integrated Radon-tight/Clean Room installation. Robin Lafever

  3. Scenario 1 The generic ‘Radon Box’ The box concept treats the Radon Barrier and the Clean Room structure as two separate systems. This treatment avoids potential problems of modifying or adapting a conventional Clean Room to also act as a Radon barrier, and isolates their functions. Some assumptions and constraints are: Clean Room construction and assembly will occur after the structural steel work is in place, the external Hut skin is installed, and may overlap with Cryostat assembly and commissioning. All work will be done inside the installed Hut skin, if possible. Radon barrier materials and joint details are not subject to Radon permeability. Barrier materials are selected with assembly techniques in mind. Radon box construction is assumed to be all welded joints, no glued or bonded joint details. Candidate materials include Stainless steel, Galvanized steel, polypropylene, polyethylene, and possibly copolymer Food packaging films, all of which have a practical welding technique appropriate to the material. Material thickness is selected to avoid significant Radon contribution through permeation. Air handling and filtration equipment will utilize the ‘Balcony’ deck, above the Clean Room roof and adjacent to the Faraday cage. All the Clean Room structures and hardware are inside the Radon Barrier. No penetrations through the Radon barrier. All utility penetrations through the Radon barrier are installed with vacuum feed-thru fittings. Radon-Free Air can / will be pumped directly to the critical working area. Robin Lafever

  4. Topics The basic ‘Radon Box” 300 K Flange modifications Timing Scenario 1 Exterior Ductwork Scenario 2 Interior Ductwork Scenario 3 Clean Room Zones Scenario 4 Radon Barrier Zones Doors Robin Lafever

  5. The basic ‘Radon Box” Radon Barrier installed As a single sealed unit, the ‘Radon Box’ This face is transparent to show ductwork connecting the Air-handling Bay to the main Radon Box structure Robin Lafever

  6. The basic ‘Radon Box” The current Clean Room in place Robin Lafever

  7. The basic ‘Radon Box” The current Clean Room in place with the Radon box cut away . In this concept, Clean Room Air handling, ductwork and ceiling filters and floor vents are all installed independently inside the Radon Box Robin Lafever

  8. The basic ‘Radon Box” Default Clean Room installed. Supply air goes into the ceiling and return air goes through the floor, back to the equipment Bay on the ‘Balcony’. Robin Lafever

  9. The basic ‘Radon Box” The Radon Box is a single continuous skin (with the exception of the 300 K Flange area and shield access hole in the floor) Note that columns are outside the Radon Barrier. The interior is isolated from Radon emanation from the steel building structure, and vibration isolation from the cryostat support columns is no longer needed. Robin Lafever

  10. The basic ‘Radon Box” There is some limit on where exterior ductwork can be placed. This configuration shows the duct between the CUORE hut and The CRESST building. Robin Lafever

  11. The basic ‘Radon Box” The ducts could be expanded into a plenum under the floor, however, this is a busy area, with utilities, lighting, and a Crane system on the ceiling of the lower floor. Robin Lafever

  12. The basic ‘Radon Box” Robin Lafever

  13. The basic ‘Radon Box” Robin Lafever

  14. The basic ‘Radon Box” Robin Lafever

  15. The basic ‘Radon Box” Robin Lafever

  16. Timing Robin Lafever

  17. Timing Robin Lafever

  18. Robin Lafever

  19. Timing Robin Lafever

  20. Robin Lafever

  21. Timing Robin Lafever

  22. Timing Robin Lafever

  23. 300 K Flange modifications Robin Lafever

  24. 300 K Flange, MODIFIED In addition, feed-through assemblies are required for the Lifting assembly. The radial position and feed-through details are not known at the moment, but this treatment shows Radon Seals and cables inside the adapter flange. Robin Lafever

  25. 300 K Flange, MODIFIED Bottom view Note that the Suspension assemblies Are potential Radon leaks and need seals. The details are not known to me, however, I Show an assembly that could incorporate O-ring packing glands. Robin Lafever

  26. Top section view showing Suspension hardware, Cable feed-throughs, and the adapter Flange with Radon Barrier/vibration isolator Note that the feed-through will need some radial space, TBD. Robin Lafever

  27. Bottom section Again, note that the suspension Hardware needs a Radon seal Again, this is a potential Radon leak And will need some kind of seal. I do not know what the actual details are. Robin Lafever

  28. 300 K Flange modifications Robin Lafever

  29. 300 K Flange modifications Robin Lafever

  30. 300 K Flange modifications Robin Lafever

  31. Robin Lafever

  32. 300 K Flange modifications Robin Lafever

  33. Robin Lafever

  34. 300 K Flange modifications Robin Lafever

  35. Scenario 2 Internal Ductwork Robin Lafever

  36. Scenario 2 Internal Ductwork Robin Lafever

  37. Scenario 2 Internal Ductwork Robin Lafever

  38. Scenario 2 Internal Ductwork Robin Lafever

  39. Scenario 2 Internal Ductwork Robin Lafever

  40. Scenario 2 Internal Ductwork Robin Lafever

  41. Scenario 2 Internal Ductwork Robin Lafever

  42. Scenario 3 Clean Room Zones Robin Lafever

  43. Scenario 3 Clean Room Zones Robin Lafever

  44. Scenario 3 Clean Room Zones Robin Lafever

  45. Robin Lafever

  46. Scenario 3 Clean Room Zones Robin Lafever

  47. Scenario 2 Internal Ductwork Robin Lafever

  48. Scenario 2 Internal Ductwork Robin Lafever

  49. Scenario 4 Radon Barrier Zones Robin Lafever

  50. Scenario 4 Radon Barrier Zones Robin Lafever

More Related