1 / 8

g2p/ GEp Beamline Status

g2p/ GEp Beamline Status. Tim Michalski Project Lead. Overview. Facilitate the design, procurement, and build of the beamline – up to the target chamber Experimental Plan Project Overview Project Status Project Challenges with risk mitigation. Experimental Plan. Project Overview.

misu
Télécharger la présentation

g2p/ GEp Beamline Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. g2p/GEp Beamline Status Tim Michalski Project Lead

  2. Overview Facilitate the design, procurement, and build of the beamline – up to the target chamber Experimental Plan Project Overview Project Status Project Challenges with risk mitigation

  3. Experimental Plan

  4. Project Overview • Design, procurement, component calibration and testing • Now through May, 2011 • Some components arrive after May • Access to Hall A for installation • May 14, 2011 • Installation completion – start of Physics • November 14, 2011

  5. Project Status • Regions 1 and 2 designs complete and material ordered • Region 3 design well underway • New FZ vacuum chambers on order – Due this month • Finalizing FZ magnet stand designs • Addition of Harps on Articulating Arm and upside down girder • M15 style BPMs rather than stripline • Calorimeter controller repaired and SW upgrades underway • Worked through issues on BPM and BCM • Requires 12 BPM “Transport” modules • Awaiting testing to validate design decisions

  6. Project Challenges • Instrumentation for Low Current data • BPMs and BCMs • Mitigation • BPM – M15 style, new electronics, test to verify this will achieve needed results • BCM – use existing hardware, test to verify this will achieve needed results (planned for mid Feb.) • FZ Magnet PS requirements evolving • Need up to 8 kG, requiring465A • Mitigation – reflecting requirements against selected PSs, identifying potential alternates

  7. Project Challenges • Acquisition of equipment from various sources • FZ magnets, corrector magnets, slow raster, new BPMs, power supplies, controllers • Mitigation – get control as soon as possible, test and calibrate early (before installation) • Resurrection of Tungsten Calorimeter • Reposition in beamline, re-establish functionality, recalibrate • Mitigation – SW resource already assigned

  8. Project Challenges • Installation at the same time as 12 GeV upgrades during 6 month down • Mitigation – alerted groups which will be in high demand – schedule planning in process • Slow Raster issues raised at last collaboration meeting – waveform generators and “hole” in raster pattern • Mitigation – Physics Electronics group addressing, update meeting Tuesday • Maintain strong communication – highlight issues early!

More Related