1 / 20

Conventional Facilities Division Project Status Update

This update highlights the progress and events in the Conventional Facilities Division project since the last review in March 2009. It includes information on construction, contracts, injuries, risks, and milestones.

mouellette
Télécharger la présentation

Conventional Facilities Division Project Status Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CF Status Update Marty Fallier Conventional Facilities Division Director Conventional Facilities Advisory Committee Review November 9-10, 2009

  2. Outline Progress & Events Since Last Review (March 10, 09) Begin Ring Bldg construction Accelerated elements of the Ring Bldg schedule Award & issue NTP for all construction contracts (except LOBs) Award all pre-purchased equipment contracts Begin LOB design 1 year early Executed LOB design, contractor outreach and prepare RFP Experience 1st construction site injuries Scope Status - Project Change Requests - PCRs EVMS Status Cost Status & Schedule Status Risks Issues Action Items (separate PDF file)

  3. Progress • Started Ring Bldg Construction (CP-2) – • NTP March 25th, construction start April 15th • Adopted revised phasing plan accelerating Injection and RF Bldgs – no added cost • Mobilization went smoothly until an injury occurred • Carpenter fell from step ladder fracturing heel bone 4/25 • Instituted changes in field safety presence as a result • Discussed in detail in Steve Hoey’s presentation • Construction progressed ahead of baseline until combination of bad weather and adopting Torcon “Early Finish” schedule as baseline was done in July 09 • Ring Bldg has since regained most of schedule and baseline has been revised to be more realistic

  4. Progress cont’d Photo From BGRR Stack 9-21-09 Vehicle Tunnel SR Tunnel Wall Forms SR Tunnel Slab Status of construction Site at FY09 End

  5. Progress cont’d Photo From BGRR Stack 11-5-09 SR Tunnel Wall Forms Column Footings SR Tunnel Slab SR Tunnel Walls Vehicle Tunnel Ring Bldg Progress from month to month is substantial Monthly billing is ~$4M - $5M

  6. Progress cont’d • Awarded Balance of Construction Contracts – • Awarded Electrical Substation (CP-3) July 17th • Awarded Chilled Water Plant Expansion (CP-4) July 1st • Awarded Chilled Water Piping (CP-5) August 28th • Net bid results of three CP’s were within $10k of baseline • Awarded balance of pre-purchased equipment contracts • All awarded on or ahead of schedule • Delivery of equipment for each procurement running about 2-3 months ahead of schedule

  7. Progress cont’d • ARRA funds enable advance of LOB design, procurement & construction • Perform design in FY09 instead of FY10 • Start construction in FY10 instead of 12 • Complete construction FY12 ~16 months early • Enables procurement during favorable market and early occupancy by beamline staff during beamline construction • Creates some potential contractor coordination issues • Have worked closely with Torcon to minimize impacts • A/E Design nearly complete • Held contractor informational meeting – more scheduled • RFP to DOE for approval – expect release in early-mid Dec

  8. Progress cont’d • First Construction Accidents/Injuries • Progress in the sense that we need to learn from these events to prevent recurrence • 2 DART cases and one reportable plus several first aid cases to date • Each is an opportunity to improve the safety program and reduce possibility of recurrence • Numerous corrective actions have been implemented • Draft investigation report is topic of discussion/review • Steve Hoey & Ray Costa presentations later today • We welcome your comments & recommendations on how these events can be used to further improve the construction safety program

  9. FY09 Goals & Milestones • Complete Bid and Award of Major Contracts for: • Electrical Substation Expansion - Done • Chilled Water Plant Expansion - Done • Chilled Water Piping - Done • Owner Furnished Equipment - Done • Complete Readiness of Construction Mgt Team - Done • Begin successful execution of construction contracts: • Ring Building earthwork completed and start concrete & utilities - Done • Begin Chilled Water Plant foundations - Done • Begin Electrical Substation - Done • Begin CHW Piping - Done • Confirm LOB design plan & execute detailed design- underway

  10. EVMS Status - Cost & Schedule • Cost Assessment: Cumulative cost variance $+24k on~$43M or 0% On budget - CPI =1.00 • Schedule Assessment: Cumulative schedule variance $-3,811k on ~$46.8M or -8.1% - Slightly behind schedule SPI =0.92 Data up to Sept 30, 09

  11. EVMS Status - Variance Analysis • Cost Variance - None • Schedule Variance WBS 1.5 – aggregate – ($3.81M) • Ring Bldg variance (-$1.3M or -5.4%) • Contractor early finish schedule for steel fabrication is most of this • Some utility work and submittals account for balance • None affect critical path and contractor is making up ground • Chilled Water Plant Expansion (-$1.8M variance) • Electrical Substation (-$0.2M) • Chilled Water Piping (-$0.2M) • All 3 contracts scheduled for on-time completion • Baseline profile for these contracts did not reflect reasonable cost plan • PCR required to adopt contractor schedule/cost profile as baseline for each • PCR to be processed in October 09

  12. Scope Status – Project Changes PCRs • Approved changes since last CFAC 3/10/09

  13. Scope Status – Project Changes PCRs • Changes in preparation for near term • *Pending LOB bid results in 2QFY10

  14. Costs – Management & Engineering

  15. Costs - Construction • As Part of FY10 Work planning Process EAC is being reevaluated and will be corrected for Oct 09 data • Bulk of VAC is pending PCR for LOB scope, A/E LOB re-design fee & post bid addendum costs

  16. Schedule

  17. Risks • Construction safety program must be effective • Safety program enhancements after most recent injury must be maintained and developed further • Potential for field changes during construction • Site related changes nearly retired, only design related remain • Added potential for changes due to LOB & Ring contractor interface • Potential for design changes from ASD & XFD • Thus far, only very minor changes with exception of larger LOBs • Risks for procurement of balance of CF scope partially retired • CHW Plant & Pipe, Elect Substation, Elect Equip - Done($16M) • LOB procurement remains – ($~40M+ for larger LOBs) • No new risks foreseen

  18. Look Ahead • Ring Building contractor • Improved safety performance, ramp-up concrete and utility installation, expedite submittals, prepare for steel delivery and erection • Electrical Substation Expansion • Begin ductbank installation and B603 modifications • Chilled Water Plant Contractor • Install foundations, pipe headers, steel & equipment submittals • Chilled Water Piping • Defer mobilization to 3/15/10, order & deliver piping & components • Electrical equipment vendors • Prepare for in-process inspections and equipment delivery • LOB Design and Construction • Prepare bid-issue bid set • Submit draft RFP: for DOE review • Continue contractor outreach

  19. Issues • Ring Building Contract • Torcon must maintain excellent safety performance • Torcon has implemented plan to regain schedule • Torcon slow on submittal of pricing proposals for ECN’s (management currently focused on improving safety) • Utility conflicts have been resolved and utility submittals need to catch up • PCR’s in preparation for newly awarded contracts • Need to incorporate CHW Plant Expansion, CHW Piping and Elect Substation contractors cost plans into baseline for accurate performance assessment • PCRs for field changes and ECN’s need to be processed once acceptable proposals are received. • Advancing LOB Design & Construction • LOB RFP advancing more slowly than expected however, coordination of LOB contractor with Ring contractor limits start of LOB construction to no earlier than 7/1/10 – thus no impact if awarded in March 10.

  20. Conclusions • CF activities are on budget and close to on-schedule • Will be back on schedule when contracts are incorporated • Working with Torcon to get back on early finish schedule • Maintaining a “best in class” construction safety program remains a key objective • Construction proceeding well • Contractor and subcontractors are technically proficient and quality is very good • Balance of CF procurements (except LOBs) are in place or nearly so – cost results are within baseline • LOB design nearing completion and release for proposals when RFP is approved

More Related