SlideServe
Menu
Préférences
© SlideServe · v2026

Task 160 May Status Report

nevada-cervantes avatar
4 diapositives · 184 Views · Oct 25, 2014

This report outlines the current status of the 3GPP funding for FY 2001 and progress on TTCN initiatives. With a total funding of 26 million for the first half of the year, the approval for shifting funds from FY 2002 has been acknowledged. Voluntary contributions have started to roll in, including 6 million from Motorola. Despite some challenges, progress has been made with new TTCN test cases being developed. The report highlights ongoing efforts to meet June's goals and plans for discussions on budget requests for FY 2002 and 2003.

Task 160 May Status Report - slide 1
01 / 4Task 160 May Status Report
1 / 17

Télécharger la présentation

Task 160 May Status Report
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. Task 160 May Status Report Shicheng HU, MCC 07 May, 2001 TP-010134 MCC

  2. Task 160 (TTCN) - Funding • Completion of all contracts for the received 3GPP 2001 funding (26 mm) for the 1 half of this year. • PCG acknowledged the needs from TSG-T for the funding shift from FY 2002 to FY 2001 and approved the request. • A call for the TTCN voluntary contributions has been circulated within the SDOs (ref. ETSI CL 2083). • Answer deadline set to end of May, • 6 mm of the voluntary funding from Motorola received, • The remaining need for the 2nd half of 2001 will be funded by the shifted funding. • For the further spending request for TTCN project during FY2002 and 2003, requested budget (58mm with 50% extra allowance) will be discussed in October.

  3. Progress & Measures • Progress in TTCN draft • 400 TTCN test cases available in 34.123-3 v.102, • 60 new GMM test cases drafted, • TTCN for SS control largely updated in accordance with ASP update v.102 (RAB reconfiguration, security & DL channel power control) . • During Feb. – May, 3 TTCN experts were available. • Considering high CR volume in the core spec, two experts allocated for the TTCN maintenance. • Warning: the goal for 460 TTCN test cases in June will NOT reached. (estimated 410). • In order to maintain the Sept. goal to approve 34.123-3, additional 3-4 experts will be started soon. Their result is expected in August. • L2 (MAC, PDCP & BMC) tests, • Multi-cell TTCN tests (RRC measurement and idle mode), • SMS over PS.

  4. TTCN plan 2002-2003