An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Section 25 Launch Campaign . . . Rick Pickering EO-1 Instruments Systems Manager

  2. Agenda • Transportation • Launch Site Processing • Overview • Flow • Facilities • Communications • Procedure Status • Support Equipment • Launch Vehicle Interfaces • Issues • Summary

  3. Transportation • Transportation Plan (SAI-PLAN-314) - 5/20/99 • Shipping Container • Custom Designed for EO-1; Consists of Dolly and Cover • Used for Movement from Swales to GSFC; Dolly Used for Intra-Facility Movement in Buildings 7/10/29 • Shock Isolation System • Desiccant, Humidity Indicator, Pressure Relief Breather Valves, Through Fitting for Purging • Spacecraft • Bagged w/ GN2 Purge in Climate-Controlled, Air-Ride Van • Swales Mechanical Personnel in Chase Vehicle • Planned Stops to Monitor Purge • Respond to Contingencies • Shock Environment Monitored

  4. Transportation (continued) • GSE • Shipped 3 Days Prior to S/C in Climate-Controlled, Air-Ride Van • Responsibilities • Swales • Planning • Loading of S/C into Shipping Container, and onto truck • Crating of loose equipment • GSFC/Transportation Branch • Arranging commercial transportation • Installation of shock/vibration monitoring system • Final preparation and loading of EGSE racks and crates • NASA/KSC/Vandenburg Launch Site (VLS) • Unloading support • Storage of shipping container, crates, etc. • Similar approach used for movement of S/C from Bldg. 836 to Bldg. 1610 • GSFC responsible for shipping flight battery and racks

  5. EO-1 Shipping Container

  6. Launch Site Processing - Overview • Flow Similar to Many Previous GSFC Missions • Launch Site Activities Plan (SAI-PLAN-337) • Major Difference: 1st Use of Boeing Dual Payload Attach Fitting (DPAF) • Satellite • Post-Ship Checkout in Bldg. 836 • Fueling & DPAF Integration in Bldg. 1610 or TBD Commercial Facility • Launch from SLC-2W; Co-manifested w/ SAC-C (Argentina) • GSE • Initially set up in 836 • Few items move to 1610 and SLC-2W • Personnel • Primary office space in 836 • Work at 1610/SLC-2W as necessary

  7. EO-1 Launch Site Flow

  8. Building 836 • Managed by NASA/KSC/VLS • Class 100K Clean Tent • Control Room for ASIST Work Stations and other EGSE • Office area for EO-1 personnel • Storage for shipping container, etc.

  9. Bldg. 836 Lab 1 Clean Tent

  10. Bldg. 836 Lab 1 GSE Area

  11. Building 1610 • Managed by NASA/KSC/VLS • Class 100K Clean Room • All SAC-C post-ship processing performed here • Primex to fuel both spacecraft from single set-up • DPAF and Vertical Shipping Container pre-positioned • Only necessary personnel will work at 1610; offices and most EGSE remains in 836 • NASA/KSC/VLS providing man-lift for S/C access once integrated w/ DPAF • Potential availability issue

  12. Space Launch Complex 2 West • Class 100K Clean Room on Levels 5 & 6 • Only necessary personnel will work at SLC-2W; offices and most EGSE remains in 836 • All access and activities will be coordinated w/ Boeing

  13. EO-1 Launch Site Communications • Comm Requirements Straightforward • Integrated Operational Requirements Document issued by Boeing; defines requirements to Western Range (WR) • Most Comm Links rely on existing, previously used capabilities. Exceptions: • New S-Band Antenna at SLC-2 (installation/testing complete) • X-Band Splitter at 836 (checked out; final installation after IMAGE launch) • New GPS Antennas at 836 and SLC-2 (checked out; final installation after IMAGE launch) • Umbilical Rack Reset in Remote Launch Control Center: Boeing provides interface for Swales control box; plan is to install/checkout after S/C arrival at VAFB • S-Band and S-Band links between 836 and SLC-2 must be shared by EO-1 and SAC-C; no unavoidable conflicts expected

  14. Planning/Procedure Status • Goal is to utilize I&T procedures to the maximum extent possible • Fueling Procedure has been trial-run by fueling contractor, Primex • Contingency Planning • Defueling • Launch Scrub • Missile System Pre-launch Safety Package (MSPSP) delivered to both 30th Space Wing and NASA/KSC/VLS Safety Offices

  15. GSE Status • EO-1 requires relatively little GSE • All EGSE remains in Bldg. 836, except: • Umbilical Rack: Will be moved to SLC-2W Electrical Equipment Building (EEB) while S/C being fueled • Battery Racks: Will be used in Bldg. 1610 and on pad (located on Level 3) • No GSE used by EO-1 at VAFB for first Time by EO-1, except: • Battery Cooling Cart: Being Provided by NASA/KSC (Used by GGS/Polar); GSFC unit too large for use on Mobile Service Tower (MST)

  16. Launch Vehicle Integration • Delta II/EO-1 Mission Specification: • To be issued by Boeing by end of Dec; no issues expected • Requirements verification needs to be completed by Boeing • Coupled Loads Analysis - completed; all loads within design limits • Dynamic Clearance Analysis - completed; significant margins • Schedules - Boeing’s Countdown Bar Charts in good shape for this stage of program

  17. Launch Vehicle Interfaces • Payload Attach Fitting (PAF) provided by Boeing • Fit check w/ flight PAF successfully completed • 100 lbs springs instead of standard 200 lbs springs needed due to EO-1 mass and CG off-set • T-0 Umbilical Harness • Flight harness mated during PAF fit check • Flight mate will be be done as part of DPAF integration • Dual Payload Attach Fitting (DPAF) • First flight • Qual program and pathfinder complete

  18. Launch Vehicle Interfaces (continued) • Environmental/Contamination • “Whiteroom”: Class 100K, 65-75oF, 35-65% R/H • Fairing Air: Class 10K, 55-60oF, 35-65% R/H • Spacecraft Access • MST Level 6 - Adjustable height; must be shared w/ SAC-C on limited occasions • Diving boards/platforms provided by Boeing • 2 24” Fairing Access Doors • GN2 Purge Line Installation (Fly-away purge) • Battery Cooling Duct Installation Removal • GSE • Battery racks on Level 3 • Battery cooling cart on Level 6 • Umbilical Rack in EEB

  19. Issues • Bldg. 1610 may NOT be available due to potential conflicts with IMAGE and NOAA-L • IMAGE may not be out of 1610 when SAC-C begins to arrive • NOAA-L needs 1610 3/1/00 for 5/9/00 Launch; may slip • Held initial discussions with potential commercial facility providers: Astrotech and SSI (SLC-6) • Astrotech accommodates existing plans essentially w/o change • SSI requires changes to both equipment and procedures (e.g., fueling equipment and proc, EGSE cable lengths?)