SIS 2006 Update May 24, 2006
Big Picture • Design Phase • Preparatory Projects Phase – April 24 – August 4 • Configuration Documentation & Testing • Reconfigure K12/HAN/Library, Co-locate w/ Internet provider, local projects • Implementation – ?August 5?– ????? • Details to be determined…again
Current Risks/Issues • Grand Forks Fiber • Delays in getting approvals and sign-offs • Assume redundant fiber link will not be available by rollout • Continued delay in DCN turnover • Revising rollout again • Focus on minimizing impact to HE & K12
Good News • Equipment is starting to arrive • Lab is up and configuration & testing has begun
More Information • Next IVN Session = June 28 • www.stagenet.nd.gov/projects/infrastructure/index.html • Biweekly status reports • Conceptual diagrams • Dirk Huggett • dhuggett@nd.gov • 701-223-2248