1 / 23

Monolithic suspension development

This activity plan outlines the development and integration of monolithic suspensions for a detector. It includes tasks such as steel and fiber wire suspension, setup preparation, bonding and loss tests, resistance to shocks, dust pollution, and humidity. The plan also includes tasks related to assembly, integration, and transportation of the suspension prototypes, as well as safety and transport studies.

scottgarcia
Télécharger la présentation

Monolithic suspension development

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Monolithic suspension development Activity plan Piero Rapagnani Detector meeting 30-01-2008

  2. 1) Steel wire suspension • 2) Fibre wire suspension • (new C assembly procedure) • 3) Complete monolithic suspension Set-up preparation Delivery of fused silica parts Bonding tests Loss tests Complete monolithic suspension Resistance to shocks Resistance to dust pollution Resistance to humidity Silica Dust Containment Storage Transport Three Parallel Tasks

  3. 1) Steel_proto_assembly 200828/01 - 28/02 • New RM prototype (Aluminum,ready) • New MAR prototype (PVC arms, ~ready) • Dummy MI (Al, black, existing, side flats to be machined,~ready) • Wires 200 m (ready) • Spacers (Al, to be machined) • RM coils (~ready) • Mounting (non standard) Assembly check and integration of new marionette and new reaction mass.

  4. 2) Steel_proto_LC 200801/03 - 30/04 • LC setup (Control chain calibration, basic control tests). Remarks: - control-DAQ crate ~ready (ADC config, CCD to be tested !!!) - CD crate to be installed. Test of new marionette and new reaction meas.

  5. 3) Fiber_NewEarOld_preparation (Old design revised, delivered in Feb-08)200811/02 - 30/04 • Improved mounting tools (optimizing C-tool design). • Background activities: - fibre production - fibre tests and systematics - training for EGO support Remarks: - CO2 laser performance checked and realigned. - bending point measurement machine ready. Assembly feasibility technique preparation.

  6. 4) Fiber_NewEarOld_integration200801/05 - 31/05 • Unmount Proto_steel suspension. • Assembly Dummy Mirror, new_RM, new_MAR, fibres (using specific C-tool developed). • Leave 1 week in the assembly frame. • Integration and transport in the LC facility. Suspension prototype integration.

  7. 5) Fiber_NewEarOld_LC200801/06 - 31/07 • TF measurements • Control tests • Roboustness tests. Suspension prototype Local Control test. 1st Milestone

  8. 6) Fiber_NewEarNew_preparation(New design, meant to separate weldingfrom bonding, delivered in May-08)200801/02 - 31/8 • Improvement of the mounting tools. • Pieces delivery. • Bonding (silicate/water-glass) & losses tests. • Suspension parts assembly. • Background activities: - fibre production - fibre tests and systematics Assembly feasibility and technique preparation.

  9. 7) Fiber_NewEarNew_assembly_integration200801/09 - 31/10 • Suspension and roboustness using the assembly frame • 1Week (min) stand. • assembling using the payload prototype RM, MAR Suspension in the frame 2nd Milestone

  10. 8) Safety and Transport studies Mar/08 - Feb/09 Completion of the monolithic suspension facility, an open task: hard to delineate methods beyond “conservative and reasonable”. • Infrastructure design • Orders • Construction • Implementation… Call for other EGO/Virgo collaborators ????

  11. 9) Best_Fiber_XX_LC2008 01/11 - 31/12 • Decision about the destiny of prototype with OldEarNew suspension (if still there). • Integration of the NewEarNew suspension (if 2nd Milestone OK) in the LC facility. • TF measurements. • Control tests. • Roboustness tests. Integration of the best solution found in the LC facility 3rd Milestone

  12. Draft of the planning

  13. Further support ? • (from EGO) • more technical support from local workshop and trained for skilled works (e.g. welding) • + • infrastructure and safety • (already involved, but could be officially appointed) • + • operator for routinary production works once (fibres/quality/systematics) people

  14. Present suspension critical parts • Fiber handling may induce damages on their surfaces • Silicate bonding is strongly stressed by the weldling • Welding the fiber on the lower clamp may induce cleaning problems

  15. New monolithic design Upper clamp FS bar Lower clamp

  16. New monolithic design - 2 CO2

  17. New monolithic design - 3

  18. Stress distribution

  19. Reaction mass

  20. l MACHINE Measurement of FS fibres bending length

  21. l MACHINE MEASUREMENT OF THE BEDING POINT: Referred to the tip of the fibre at both the ends Problems during the welding operation OTHER MEASUREMENTS POSSIBLE WITH THE MACHINE First violin mode Vertical bouncing mode Measurement of FS fibres bending length with respect to the tip NEXT: Full characterization on a set of fibres pulled with the CO2 laser

  22. l MACHINE Measurement of FS fibres bending length

More Related