70 likes | 186 Vues
The SIS 2006 Update outlines the current implementation phases and migration schedule as of September 27, 2006. The design phase is complete, and preparatory projects are underway. Migration began on September 18 and is scheduled through November 25, with specific timelines for ATMs, PSD, K12, and HE systems. Testing has concluded, and we are waiting on the sprint collocation rack while ensuring all protocols are followed. For assistance, reach out to our Customer Service Desk, and join the next IVN session on October 25 for more information.
E N D
SIS 2006 Update September 27, 2006
Big Picture • Design Phase • Preparatory Projects Phase • Implementation – Began migration on Tuesday • Overall schedule has not changed
Implementation • Sept 18–Oct 6 – Test & Migrate Bismarck-Fargo ATMs to RPR • Sept 25–29 – Burn-in time for RPR, Prep for PSD migration • Sept 30–Oct 6 – Migrate PSD • Oct 7–14 – Migrate I2 and prep for K12 • Oct 16–Nov 3 – Migrate K12 • Oct 23–28 – Migrate K12 Video • Oct 23 – Nov 17 – Prep & Migrate State • Nov 4–Nov 25 – Prep & Migrate HE
Current Risks/Issues • Sprint Collocation – Waiting on rack
Good News • All testing completed • Migration started • Contact our Customer Service Desk at 701-328-4470 if you experience any issues.
More Information • Next IVN Session = October 25 • www.stagenet.nd.gov/projects/infrastructure/index.html • Biweekly status reports • Presentations • Dirk Huggett • dhuggett@nd.gov • 701-223-2248