1 / 16

Mechanical Systems Mechanical / Thermal Hardware July 2005 Status

Mechanical Systems Mechanical / Thermal Hardware July 2005 Status. Marc Campell, Subsystem Manager. SLAC Status. Grid Qual Static Load Test. Hardware Grid Box assembly is 99% complete All GSFC and Spectrum provided hardware is on hand Pre-Test (SLAC activities)

skylar
Télécharger la présentation

Mechanical Systems Mechanical / Thermal Hardware July 2005 Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mechanical Systems Mechanical / Thermal HardwareJuly 2005 Status Marc Campell, Subsystem Manager

  2. SLAC Status

  3. Grid Qual Static Load Test • Hardware • Grid Box assembly is 99% complete • All GSFC and Spectrum provided hardware is on hand • Pre-Test (SLAC activities) • Test Interface Plate (TIP) Assembly delayed due to personnel conflicts with ACD operations – in work now • Need to return Spectrums Interface plate by mid-Sept. • Shipping container for Grid 2 on TIP due 9/7/05 • Test (NTS activity) • Component flexure test required to proof load flexures prior to integration with the Flight LAT on the Test Interface Plate has been added to NTS SOW • Test performed on TIP assembly prior to SLT • Flexure strain gages also characterized for LAT sine vibe testing • NTS has evaluated final load cases and additional test above and submitted delta cost proposal (+$XXK) which is still within original budget

  4. Grid Qual Static Load Test Schedule

  5. Drawing Release Plan • 66 of 73 (90%) drawings released • 3 MLI drawings (in work) • 4 unreleased parts not needed until Radiator fit check • Known drawing revisions

  6. Concerns • Lockheed Martin - Radiator delivery schedule • See LM presentation • Completion of Grid Thermal Control System hardware installation delay until Sep 05. • Will try to perform on a non-interference basis, but may impact LAT schedule. • Heater bonding fixture trials underway in I&T

  7. Open Flight Design Issues • Radiator integration sequence • Coupon testing of repeated make & break of joint has been tested. Results were inconclusive due to test facility problems. • Test facility alternatives under investigation. • Disassembly facilitated by use of mold release agent • Baseline process used for LM Radiator thermal vacuum test set up • Radiator vibration requirements • Sine vibration testing will not be performed at LM • Test options under investigation

  8. MECH Qualification Program

  9. Gamma-ray Large Area Space Telescope Cost/Schedule Reports for 4.1.8 Mechanical Systems Presentation July 2005 Month End

  10. Level 3 Milestone Count

  11. Level 3 Milestone List

  12. Milestone Variance Explanation Radiator RFI -36 days • Schedule Impact • No impact to LAT schedule • Cost Impact • LM requested additional funds to complete Radiator testing • Discussions between GLAST, LM and GSFC were held

  13. Cost Report

  14. Cost Variance Explanation • Why overrun/underrun? • LM has overrun their contract • Proceeding with Radiator testing while cost issue is being worked • What will be done to correct? • Additional funding required

  15. FTE Report (DOE/NASA-funded only)

  16. FTE Variance Explanation • Why overrun/underrun? • Delay caused by late start of Grid Box #2 assembly work • What is the impact? • Delay in Grid Static Load Test • No LAT impact

More Related