Conventional Facilities for MMF: Facility Design Criteria, Space Requirements, and Building Criteria
170 likes | 198 Vues
This presentation outlines the design criteria, space requirements, and building criteria for a conventional facility dedicated to Undulator magnet tuning, magnet measuring, fiducialization, and storage. The presentation covers aspects such as site location, environmental stability specifications, utility requirements, and resultant building criteria.
Conventional Facilities for MMF: Facility Design Criteria, Space Requirements, and Building Criteria
E N D
Presentation Transcript
Conventional Facilities – MMF Presentation Outline • Facility Design Criteria • Site Location • Facility Design • Schedule
Facility Design Criteria • Facility Use • Space Requirements • Environmental Stability • Temperature +/- 0.1 deg. C. • Humidity • Vibration <0.5 microns • Utility Requirements • Electrical • Other
MMF Facility Uses • Undulator magnet tuning – 2 magnet measuring machine test stands • Aligned with same orientation to Earth’s magnetic field as LCLS Undulator Hall. • Undulator fiducialization – large coordinate measuring machine • Cradle assembly area • Magnet storage/temperature acclimation • Work desks in lab and office space for 2 employees
Resultant Building Criteria • ~4800 sq. ft. floor space (inc. ~3000 laboratory space) + mezzanine • Locate within an existing building to aid in temperature control • Adequate ceiling height for overhead cranes • Accessible for magnet delivery using trucks and forklifts • Availability of required utilities, esp. electrical service – 600A, 480v 3f
Building 081 Location LCLS Undulator Hall Research Yard PEP Ring Road
New Space Allocation for Bldg. 081 Offices SHIPPING & RECEIVING VEHICLE SHOP EQUIPMENT REPAIR
MMF Ground Floor Plan Magnet Measuring Lab ~1600 ft. sq.
MMF Ground Floor Plan Coordinate Measuring Area ~ 1000 ft. sq.
MMF Ground Floor Plan Cradle Assembly Area ~325 ft. sq.
MMF Ground Floor Plan Magnet Loading and Storage ~850 ft. sq.
Mezzanine Floor Plan Mezzanine for Mechanical Equipment
Rear Elevation Mechanical Access Staff Access Roll up door for magnet delivery
Schedule • Completion of Title II drawings • December 2004 • Bid and contract with general contractor • January – April 2005 • Construction • May – November 2005 (Early Finish) • February 2006 (Beneficial Occupancy)