Status Update on Conventional Facilities for LCLS Installation and Commissioning

DESCRIPTION

This report provides an overview of the current status of the Conventional Facilities for the Linac Coherent Light Source (LCLS). It covers key elements related to staffing, the construction schedule, and remaining issues faced during the installation and commissioning process. Significant milestones, including the first light in the front end enclosure (FEH) and the installation of undulators, are highlighted. The document also outlines the timeline for operations and commissioning, including completion dates for critical facilities and preparation for beam commissioning.

1 / 17

Télécharger la présentation

Status Update on Conventional Facilities for LCLS Installation and Commissioning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Conventional Facilities Status LCLS Conventional Facilities Introduction Key Elements Staff Schedule Construction Status Remaining Issues

  2. LCLS Installation and Commissioning Time-Line InstallUndulators First Light in FEH LTU/Und Install X-Rays in NEH First Light in FEE CD-4 (7/31/2010) FEE/NEH Install FEH Hutch BO PEP-II run ends now M J F M A M J J A S O N D J F A M J J A S O N D J F M A M J J D D A 2008 2009 2010 Down Down? PPS LTU/Und Comm. NEH Ops & Commissioning Linac/BC2 Commissioning Re-establish e- to SL2 FEL/FEE Commissioning Nov. 3, 2008

  3. Substantial Completion Dates Central Utility PlantNOV 08 Undulator HallNOV 08 Beam TransferNOV 08 Near Experimental HallNOV 08 Beam DumpNOV 08 Front End EnclosureNOV 08 Xray/DiagnosticsNOV 08 Far Experimental HallNOV 08

  4. Equipment Warranties Equipment Testing Reports Mark up Drawings and Specifications Subcontractor Financial Records Final Acceptance Records

  5. Beam Transport Hall

  6. Undulator Hall

  7. Electron Beam Dump Area

  8. Access Tunnel

  9. 20 ITEMS REMAINING

  10. CF Construction Organization

  11. Summary • Substantial Completion has been achieved. • Punch list items are currently being addressed. • Installation tasks were successfully supported with Beneficial Occupancy and logistics under CF direction. • All systems accepted and ready for transfer to installation or laboratory service groups. • Plans are in place for the beam commissioning program.

  12. End of presentation