CONVENTIONAL FACILITIES STATUS
240 likes | 398 Vues
CONVENTIONAL FACILITIES STATUS. Jess Albino – Associate Project Director for Civil Construction June 9, 2009. Agenda. Status of Conventional Construction Turner Contract CF Remaining Work Turner Contract Closeout Office Space Procurement. Research Yard. Research Yard.
CONVENTIONAL FACILITIES STATUS
E N D
Presentation Transcript
CONVENTIONAL FACILITIESSTATUS Jess Albino – Associate Project Director for Civil Construction June 9, 2009
Agenda • Status of Conventional Construction • Turner Contract • CF Remaining Work • Turner Contract Closeout • Office Space Procurement
LCLS CF Work Remaining • Construct Experimental Hutches in Far Experimental Hall • Structural Steel in fabrication – installation begins in June. • Build-out contract in award stage – NTP in July. • Office Space Alternatives Project • Baseline Change approved – construct new building • Design/Build, Guaranteed Maximum Price contract • Contractor selected – NTP in June
WBS 1.9 Completed and Remaining Proc/Fab/Assy 11,285,208 Dsn/Engr 909,466 Admin/Mgmt 1,302,273
Turner Contract Closeout • Notice of Substantial Completion 11/17/2008 • Notice of Completion ~4/24/2009 • Remaining Activities • Redline mark-ups sent to Jacobs for Record Drawings • 23 of 26 trade subcontracts require closeout binders • Retention amounts to be released upon closeout • Complete Lessons Learned
CF CMGC Stewardship – Lessons Learned • October ’06 thru April ’07 Ramp Up to Full Production : Procedural Violations • Stand Down of Construction Activities : All Hands Meeting • Review of Work Planning Process for field work – JSA process inadequate • PMT changes • Deficiency Notices • May ’07 thru November ’07 Full Production : DARTs • Multi-day Stand Down of Construction Activities : Corrective Action Plan • Paperwork ineffectively utilized by CM/GC and trade contractors • PMT changes • Deficiency Notices & Fines • Communication with Corporate TCCo • Safety Stewardship Committee Established • Full time on-site medic (+30hr OSHA) • UTRs added • December ’07 thru April ’08 : Some progress, then… • Two DARTs associated with one sub • PM removed • Work stopped • May ’08 thru December ’08 : No DARTs • Effective work planning & execution sought • Plan for joint observation developed • Attendance at daily morning work planning meetings • JSA review with workers throughout the day • Identification / monitoring of specific trades or tasks for safe work practices