1 / 5

Vertical Test Stand Update

Vertical Test Stand Update. C.M. Ginsburg (Fermilab) For the VTS group: C.Sylvester, Y.Huang, R.Nehring, J.Ozelis, T.Peterson, V.Poloubotko, R.Rabehl, I.Rakhno, C.Reid, M.Wong 05.October.2006. VTS Cryostat. Two bids received: Meyer Tool and PHPK

taran
Télécharger la présentation

Vertical Test Stand Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Vertical Test Stand Update C.M. Ginsburg (Fermilab) For the VTS group: C.Sylvester, Y.Huang, R.Nehring, J.Ozelis, T.Peterson, V.Poloubotko, R.Rabehl, I.Rakhno, C.Reid, M.Wong 05.October.2006

  2. VTS Cryostat • Two bids received: Meyer Tool and PHPK • After technical & price bid evaluation, PHPK selected • Purchase order placed Sept. 20 • PHPK: • ASME code calculations done for pressure vessel • Minor changes to design requested – they await our approval • Not affecting schedule • Will receive instrumentation (liquid level sensors, thermometry, etc.) and J-T heat exchanger from us in the next few weeks • C.Sylvester and T.Peterson very useful visit to PHPK Sept.26 • Will deliver status in ~biweekly teleconferences • Cryostat top plate • Baseline design near final • Some top plate is needed for pressure vessel ASME code stamp, not necessarily one we will use for testing cavities • However, top plate for testing will also need ASME code stamp • Preferable to do both at once • Delivery by March 2007 C.M. Ginsburg ILC/SRF mtg

  3. More Vertical Test Stand Activities • Magnetic Shielding (room-temperature & 2K) • Detail designs in progress • Plan Request for Proposals to include some design work • Meet with J. Zweibohmer and Procurement within ~week • Radiation Shielding • Calculations for “final geometry” in progress • Shielding lid movement design in progress • Plan radiation shielding assessment review within ~month • Kamran Vaziri (ES&H) will be our point-of-contact for radiation safety and permissions • RF System • Response to RF Review committee Sept.11 • All procurements have been placed • 500W amplifier to be shipped October 5, when tests complete • RF personnel safety interlocks in progress, with Chuck Worel (AD/ES&H) C.M. Ginsburg ILC/SRF mtg

  4. Still More VTS Activities • 9-cell temperature map (not baseline VTS) • Aseet Mukherjee • Conceptual design completed • Few cheap diodes ordered for R&D • Wish to test parasitically in A0 3.9 GHz vertical test • MS Project file update for Ken Domann (and us) in progress C.M. Ginsburg ILC/SRF mtg

  5. Reminder: Project Scope • Single, bare 1.3 GHz 9-cell Tesla-style cavities • Cryo capacity ~125 W at 2 K • Measure Q vs. T (Tmin~1.5 K) • Measure Q vs. Eacc at 2 K • 250 W (CW) max RF power required (Q>5x109, Eacc<35 MV/m) • Maintain “Controlled Area” status in IB1 • < 5 mrem/hr immediately outside the shielding • <0.25 mrem/hr in normal working areas • Foreseen upgrades: • Thermal mapping system, variable input coupler, 2nd cavity test capability C.M. Ginsburg ILC/SRF mtg

More Related