SlideServe
Menu
Préférences
© SlideServe · v2026

PIP Update: April 23, 2014 - Project Status and Budget Overview

ziya avatar
7 diapositives · 218 Views · Aug 13, 2014

The April 23, 2014 PIP Update covers the status of various projects, including Linac upgrades, modulator work, and Booster beam developments. Key updates reveal progress in linac laser notching, modulator cell builds, and booster RF projects. Discussions include budget issues, upcoming meetings, and future plans, such as new tuner designs and solid-state installations. With a focus on continuous improvement and collaboration, this summary emphasizes critical tasks and responsibilities moving forward.

PIP Update: April 23, 2014 - Project Status and Budget Overview - slide 1
01 / 7PIP Update: April 23, 2014 - Project Status and Budget Overview
1 / 17

Télécharger la présentation

PIP Update: April 23, 2014 - Project Status and Budget Overview
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. PIP Update April 23rd2014

  2. Agenda • Summary Update • Current Activities/Updates • Ken Domann – Project Status and Budget • Matt Gardner – Linac LCW upgrades & Transformer Install

  3. Update • Linac SBK: Work progressing (CDR in June) (Working on items discussed during phone conference) • Linac Laser Notching: Received the final amp – some issues which required vendor support (not fixed) • Modulator work: EE support is proceeding with build up of 25 cell (9 cell looks good) • Linac Beam Physics: No news • Injector: Both sources up and running – next will work on larger volume source and gas mixture • Booster Beam: • Transverse damper – no news • Cogging software work continues – testing on MI cycles continues, notch creation using new system verified • Booster optics software – verification of 465 cards complete this week – testing this week tune settings • Booster Longitudinal dampers - progress continues – verification of process ( see pics) • Booster RF • Booster RF2 Cavity shipped last Friday – work will start this week on it? • RF19 – all assembled (replaced vacuum flange) - finishing up dressing cavity before testing • Looking at extra tuners (one that was stored in box and one on large bore cavity) • New Parallel Cavities – Waiting on temp measurements (some done on last cavity) • Perpendicular Cavities – working on solenoid design and testing of ferrites – buying samples • High mu cores – the rest of our sample High U cores should be here? Verify them this week! • Additional pieces will allow us to to build single tuner • Assemble three tuners and put on spare cavity – then test!! • Booster Anode Supplies –Work continues – headaches with purchasing!! • Booster Bias supplies – First one had to have some LCW re-work but is close to finish • Booster Shielding – setting up another round of scans – during cavity install & next day • Booster Nothcer – TD proceeding with building 2 more short kickers, Work on PS testing continues • May convert to new PS system during shutdown for one long kicker!

  4. Install refurbished cavity in slot 2 Pull Cavity RF 5 (need to fix taper) Pull another cavity for refurb • Cavities Refurbishment • 10 of 19 cavities have been refurbished

  5. Recent PIP Budget/News • Budget Issues: no news from DOE/Lab meeting • Another budget meeting in June (after dust settles) • General: Lots of talk about P5 and DOE – PIPII/PIP • PMG – 4/26 has been canceled – Stuart is departing • Who will replace Stuart – not sure but he has listed PIP as one of his important tasks • Lots of shutdown talk – Regular SD planning • Update of RLS – some Booster items remain • P5 should report back to lab in April – PIP impact likely • Director is interested in 20 Hz – potential users….. • Too soon to affect what we are doing • Post-Doc position for PIP is open/receiving resumes

  6. Upcoming Talks Future Meetings to be Scheduled: • Eddy – Booster damper plans (next week?) • Tom Kubicki – New Booster Cavity Plan • ?? – New tuners – plans/ideas • Bill Pellico - Loss Scans and Shielding Assessment • John Reid - Solid State Installation - Final Report