LBT Q4 2007 Engineering Review

This report highlights the power installation and monitoring progress at Site PWR as of Q4 2007. Key updates include the completion of the power for the machine shop on Level 3 and the installation of power and lights, which are now operational. Power support for the LUCIFER and LINC closed-cycle cooler compressors on Level 4 is also complete. Issues with phase imbalance on UPS power panels have been addressed. Planning for 2008 includes the installation of a power connection point for PEPSI, along with ongoing power quality monitoring.

chanel
Télécharger la présentation

LBT Q4 2007 Engineering Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PWR: Site electrical power, includes power install on levels 1, PEPSI bridge, and 4, and power monitoring LBT Q4 2007 Engineering Review

  2. Highlights (Q4/2007) Instrument room power installed by contractor Machine shop moved to level 3L Power and lights on 3L complete and operational Level 4 power to support LUCIFER and LINC closed cycle cooler compressors is complete Power monitoring continuing Monitoring PF, talked with Gilbert Electric Phase imbalance corrected on UPS power panels Materials in hand to install LBTI closed cycle cooler compressor power and connector

  3. Open Issues Technical None Schedule Scheduled for 2008 Financial None Resource Materials in hand, time slot required to complete

  4. Progress (Q4/2007) Instrument room complete Power to level 3L machine shop complete Power to level 4 power expansion complete except for LBTI added requirement PEPSI power being installed

  5. Planning (Q1/2008) Install connection point power for PEPSI at bridge location Continue monitoring power quality