LBT Q4 2008 Engineering Review

LBT Q4 2008 Engineering Review. HPOP Hardpoints Study and Rework. Highlights (Q4/2008). Conceptual design of Super Hardpoint completed Actively collaborating with the LSST engineering group designing the super-hardpoints. Progress (Q4/2008).

idalia
Télécharger la présentation

LBT Q4 2008 Engineering Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LBT Q4 2008 Engineering Review HPOP Hardpoints Study and Rework

  2. Highlights (Q4/2008) • Conceptual design of Super Hardpoint completed • Actively collaborating with the LSST engineering group designing the super-hardpoints. LBT Q4 2008 Engineering Review

  3. Progress (Q4/2008) • LSST engineers are doing the design work, we are meeting at least weekly to provide oversight and guidance. LBT Q4 2008 Engineering Review

  4. Open Issues • Technical • Consistency in testing • Glass safety qualified • Schedule • 1st article end Q1, test & characterize in winter, full production in spring, install next shutdown • Financial • Funding committed • Resource • 1 People LBT Q4 2008 Engineering Review

  5. Planning (Q4/2008) • Complete detailed design • Begin parts manufacture of a first article by the end of January. LBT Q4 2008 Engineering Review