LBT Q4 2007 Engineering Review

The Q4 2007 Engineering Review for the Large Binocular Telescope (LBT) highlights key advancements in the development of infrared test cameras (IRTC). Notable achievements include the successful acceptance test of Camera #1 in November, showcasing good performance and construction quality. However, the project faced challenges, including a tight schedule with a five-month delay, albeit with negligible impact. Progress for IRTC #1 and IRTC #2 involved critical optical alignment and mechanical-electrical integration, leading to future deliveries in January and February 2008.

lindley
Télécharger la présentation

LBT Q4 2007 Engineering Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LBT Q4 2007 Engineering Review IRTC – IR Test Cameras

  2. Highlights (Q4/2007) • Successful acceptance test of Camera #1 (Nov) • Good performance and well built LBT Q4 2007 Engineering Review

  3. Open Issues • Technical • None • Schedule • Extremely tight schedule – no contingency • 5 months behind schedule – negligible impact • Financial • None • Resource • None LBT Q4 2007 Engineering Review

  4. Progress (Q4/2007) • IRTC #1 • Finish Optical alignment √ • Acceptance test √ • Delivery to Arcetri (Jan) • IRTC #2 • Mechanical, electrical, Optical integration √ • Acceptance test (Feb) • Delivery to Arizona (Feb) • Better definition of FITS headers and data format LBT Q4 2007 Engineering Review

  5. Planning (Q1/2008) • Delivery of IRTC #1 to Arcetri (Jan) • SW integration test • Acceptance test of IRTC #2 (Feb) • Delivery of IRTC #2 to Arizona (Feb) • Documentation LBT Q4 2007 Engineering Review

More Related