An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GAS PURIFICATION Team Alpha Mentor: Patrick Shannon

  2. TEAM ALPHA • Team Leader: Roxana Kolatek • Corey Lee • Scribe: Shakeeta Brown • Ivan Silakov

  3. DESIGN BASIS • 3118 TPD TO FRONT END AMMONIA • 150 MW TO CHP • 1050 BTU/SCF NG TO 10,000 HOMES

  4. BLOCK FLOW DIAGRAM

  5. Pipeline gas specifications • 500 PSI • CO2 Maximum of 2-3 mol % • H2S Less than .25 grain/100 scf • Water Vapor Less 7.0 lb/MM scf • Temp Higher than • Hydrocarbon Dew Point 67.46 ºF • Water Dew Point

  6. Process flow diagram

  7. External material balance

  8. EXTERNAL ENERGY BALANCE

  9. H2S REMOVAL MATERIAL BALANCE

  10. DEHYDRATION MATERIAL BALANCE

  11. NGL MATERIAL BALANCE

  12. Equipment $$

  13. ECONOMICS • Data is incomplete • Comparing current plants that are built • NGL removal using Cryogenics: 1856.1 MM$ • Dehydration using Glycol: 64.9 MM$ • H2S removal using Amine: 55.6 MM$ • Sum: 1976.7 MM$ installed

  14. economics • So how are we going to make money? • Annual income: 225.3 MM$ • Thus the payback time would be: 8.7 years

  15. DATA FROM BOOKS • BOOKS USED • GPSA Engineering Data Book. Vol. I & II. Tulsa: Gas Processors Suppliers Association, 2004. • Guo, Boyun, and Ali Ghalambor. Natural Gas Engineering Handbook. Houston: Gulf, 2005 • Kidnay, Arthur J., and William R. Parrish. Fundamentals of Natural Gas Processing. Boca Raton: Taylor & Francis Group, 2006. • Maddox, R. N. Gas and Liquid Sweetening. 2nd ed. Norman: Campbell Petroleum Series, 1974. • Poling, Bruce E., John M. Prausnitz, and John P. O'Connell. The Properties of Gases and Liquids. 5th ed. McGraw-Hill Companies, 2001.

  16. DATA ONLINE • SOME WEBSITES INCLUDE • Wellhead Gas Informationhttp://www.lngplants.com/TurkistanGasNewsletterJuly262011.htmlNatural Gas Processinghttp://chemengineering.wikispaces.com/Natural+gas+processinghttp://en.wikipedia.org/wiki/Natural-gas_processinghttp://en.wikipedia.org/wiki/Natural_gashttp://www.natgas.info/html/gasprocessing.htmlhttp://www.naturalgas.org/overview/background.asp • MANY OTHERS CAN BE FOUND ON OUR WIKISPACE • http://gaspurification.wikispaces.com/

  17. Hand Calculations FURTHER HAND CALCULATIONS CAN BE FOUND AT: http://gaspurification.wikispaces.com/Hand+Calculations

  18. MEETING 1 QUESTIONS & ANSWERS • Ammonia Refrigerant? • Ammonia refrigerant cannot condense propane, ethane, methane • Ammonia leak could contaminate product streams • Ammonia is corrosive to copper piping • Ammonia Used In Absorber? • Ammonia is more volatile than MDEA and can slip into the exit gas • Popular with removing CO2 from the natural gas. • CO2 is being left in natural gas

  19. QUESTIONS & ANSWERS CONT. • Any pipeline specifications? • Wasn’t able to receive any information from any of the pipeline companies. Running at pipeline specs. Pressure at 500 psig • Placement of Compressor? • The compressor will be placed after amine process • Will determine after economic analysis • Propane Storage? • Thick-Wall Steel Tanks

  20. Future focuses • REMOVAL OF CO2 • ASPEN SIMULATIONS • TEMPERATURES AND PRESSURES OF PROCESS • EQUIPMENT SIZING • NEGOTIATE CONTRACT WITH SULFURIC ACID PLANT • FIND BUYERS FOR NGL’S