1 / 18

Leak Testing QC of Cold Vacuum Systems the story so far……….

Leak Testing QC of Cold Vacuum Systems the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133). Leak Testing QC of Cold V acuum Systems - What?. Phase 1 leak test – Prior to splice consolidation (Arcs, LSS, QRL)  Air to insulation vacuum

elvin
Télécharger la présentation

Leak Testing QC of Cold Vacuum Systems the story so far……….

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Leak Testing QC of Cold Vacuum Systems the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  2. Leak Testing QC of Cold Vacuum Systems - What? • Phase 1 leak test – Prior to splice consolidation (Arcs, LSS, QRL) •  Air to insulation vacuum •  Helium to insulation vacuum •  Helium to beam vacuum • Phase 2 leak test – During splice consolidation •  intermediate testing of new welds: • SIT, DFBA, DN200 – on-going • M lines – starting today • PIM – not yet started • Phase 3 leak test – After splice consolidation •  Global leak tests after re-closure, including pressure test Complete Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  3. Leak Test QC • Sequence: • Leak test executed according to procedure by trained technician, • Daily report of executed tests & results prepared by team leaders, • Result is checked by staff or COFREND certified contract support, • Result recorded and stored on TE-VSC-EIV sharepoint page, • Result recorded in WISh (where applicable), • If NOK, create NCR in MTF (staff or certified contract support), Paul Cruikshank TE/VSC Leak Testing QA SMACC QA team meeting 11/4/2013

  4. Leak Testing of Cold Vacuum Systems Phase 1 - Why?  Status of vacuum system tightness  Localisation of known leaks  Localisation of any new leaks  Leak repairs in masked time  Early warning of unexpected problems Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  5. Leak Testing of Cold Vacuum Systems Phase 1 – Helium to BV leaks Courtesy J.Finelle  Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  6. Phase 1 – Air to IV leaks Connector feedthrough 0-ring MB vessel at central foot B31L5, A21L8 C16R5, A26L7 B32L8 Foot flange o-ring C22L4 Q6L8 Jumper weld/material Q7L2 Q29R2 Q21L3 Q21R3 Q33R7 Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  7. 22 ‘known’ He leaks in IV prior to LS1 Highest priorities are: S3-4, A27L4.M, cold mass circuit S4-5 QRL SubSB, line C – repair with TE-CRG Note: - LHC operates with these leaks  - the 2 big leaks weren’t present at RT after welding & P.Test - some known leaks accepted ‘use-as-is’ due to lack of time during installation  - some known leaks weren’t found to component level despite search during installation  Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  8. Helium leak observations in IV ‘Green’ helium leak – IV pressure is rising…………. ….leak elimination will avoid perturbation to cryo system during temp transients Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  9. Helium leak observations in IV ‘Red’ helium leak – IV pressure rise & then limited by turbo pump speed… …leak elimination will reduce heat loads and avoid reliance on turbo pumps for pressure equilibrium Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  10. Phase 1 – Helium to cryomagnet IV - Correct test conditions have allowed 4 ‘known’ leaks to be discarded.  air leak near gauge, or Penning gauge error, oil vapour pressure (see later) - 4 newly observed small ‘green’ leaks may be due to correct test conditions/extra scrutiny…. - 20 internal helium leaks identified in arc subsectors after warm-up – 14 identified to component (for repair).  for 6 leaks not identified to component, further tests to be performed in phase 2. - Triplet 5L – helium leak in FF circuit (inside DFBX) stable since 2009 – propose continue ‘use-as-is’. - NC follow-up in MTF. Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  11. LT Phase 1 – internal leak types QQS current leads (x1) QBQI.9L2 (Q8) M2N flexible (x3) QBQI.18R5 QBQI.26R7 QBQI.33R3 K collector (x4) QBBI.8L7, QQBI.22L7, QBBI.B34L7, QBBI.B21R6 M weld or collar (x3) • QQBI.13L6 (M3) • QQBI.7R5 (M2) • QBBI.A29L4(M3) K flexible (x3) QBBI.B26L3, QBQI.9R2, QBEI.11R3 Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  12. Phase 1 – Helium to QRL IV LS1 foreseen objectives: - Collaborate with TE-CRG to repair known (observed Dec’ 2010) internal helium leak in S45. - Check helium residuals & air leaks after warm-up of the 72 subsectors: but, large & fast pressure rises seen in IV of 5 QRL subsectors during LS1 warm-up, 6 additional internal helium leaks confirmed (5 not present during 2013 operation), all 7 confirmed on header C at multiply compensator. - QRL analysis/action plan/repair is on-going………………….in shadow of SMACC Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  13. Phase 2 - Leak test support for M welds - Dedicated leak testing teams. - Results (to be) documented in WISH - Long clamshell tool has been developed and validated: to test 2 M welds simultaneously, to pump and backfill the 214m He volume at a predefined unwelded M sleeve, to bridge a splice NC (if left unwelded) . - Standard clamshells also available (M, SSS diode). - First subsector – 16 interconnects - released for vacuum test yesterday (22/7/2013) Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  14. Phase 2 - Leak test support to SIT - Leak testing team attached to SIT production, - Weekly meeting to review past week, next week, any issues, - Test tooling operational - optimisation is continuous process (VSC & MSC)….. - Results documented on VSC/EIV sharepoint page. Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  15. Phase 2 - Leak test support to DFBA - Leak testing team available for DFBA production, - Test tooling optimisation is continuous process (VSC & CRG)….. - Results documented on DFBA site & VSC/EIV sharepoint page. Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  16. Phase 2 - Leak test support to DN200 - Leak testing on call for DN200 production, - Baseline is to make sample intermediate testing to check process (100% phase 3test) Start of production (~35 made at S78 start) Change of weld parameters/procedure (~ 8 made), Series (5%) - Results documented in WiSH & VSC/EIV sharepoint page. DN200 weld leak (1 E-1 mbarl/s) Adjacent to QQBI.A29R8 Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  17. Phase 2 – oil & MLI observations On-going checks: TE-VSC confirms no abnormal insulation vacuum pressure in affected subsectors TE- CRG confirms no abnormal heat loads in affected subsectors. Oil composition analysis on-going – primary pump oil? Origin of oil? Incident during LHC installation tests, egmobile pump malfunction? Incident during LHC cold operation eg negative pressure gradient cryostat to fixed pump? MLI debris? May come from fast venting/vacuum break – when ? Connection between oil & MLI debris not (yet) understood. Sector 8-1 (A11L1.M & A15L1.M) & 2-3 (A11R2.M), Oil traces at several interconnects, accompagnied with MLI debris Q26L6 - oil in cryostat Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

  18. Results so far….. Leak Test summary: Phase 1: He to BV – no problems Air to IV – several NC to solve He to IV cryomagnets – 20 confirmed existing leaks, 14 localised for repair He to IV QRL - 7 confirmed compensator leaks, repair on-going Phase 2: SIT, DFBA, DN200 – ok, on-going M welds – just starting…. Paul Cruikshank TE/VSC - Leak Test QC of Cold vacuum Systems - 4th Splice Review, 23/7/2013

More Related