1 / 13

3 MeV test stand measurement plans

3 MeV test stand measurement plans. A. Lombardi for the LINAC4 team. Scope. Validate Source and LEBT design RFQ design Chopper. Source 45 keV. Chopper. Diagnostic line. RFQ 3 MeV. LINAC end-to-end. Location and causes of e growth and losses:

idola-barry
Télécharger la présentation

3 MeV test stand measurement plans

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 3 MeV test stand measurement plans A. Lombardi for the LINAC4 team BCC 41 - 3MeV test stand measurements

  2. Scope • Validate • Source and LEBT design • RFQ design • Chopper Source 45 keV Chopper Diagnostic line RFQ 3 MeV

  3. LINAC end-to-end Location and causes of e growth and losses: LEBT solenoids (divergent beam from the source). 45 keV MEBT transport (abrupt change of phase advance). 3 MeV BOTH ARE UNAVOIDABLE but they must be controlled

  4. Emittance 0-3 MeV Symmetry x,y in LEBT, if source is symmetric Losses in the RFQ, emittance decreases Losses and emittance increase when matching to the DTL

  5. bench Spectrometer (0.2 %) Slit and Grid Emittance ToF (calibration) Bunch Shape Monitor Halo Monitor (chopping eff.) Transformers Feshenko EDMS – 1004908 G. Bellodi BCC 41 - 3MeV test stand measurements

  6. Measurement plan – 1/2 BCC 41 - 3MeV test stand measurements

  7. Measurement plan – 2/2 BCC 41 - 3MeV test stand measurements

  8. MOST IMPORTANT MEAS Pencil beam All elements on Chooper on (top) Chopper off (bottom) With this we validate : • Chopper voltage • Optics we do not validate : • Space charge • Rise/fall time BEAM AT THE ws JUST BEFORE THE INLINE DUMP

  9. Measurement 2011 – p from DESY OP DAY - 26th January 2012 Archamps

  10. Protons • Already discussed – EDMS 1096658 • Measurement with Desy source in proton mode (2011) gave an excellent insight into LEBT dynamics and solenoid modelling To be done before protons are usable : • optimise to reach a min of 50-60 mA after the first solenoid, • measure emittance vs. solenoid settings (5-10) and back-trace to source input : create a beam for simulating/optimising the whole test stand. BCC 41 - 3MeV test stand measurements

  11. Sharing the test stand- proposal(change over takes ½ day to 1 day) • Run in proton mode until the emittance metre has to be dismantled • Source development till RFQ ready for beam • Share 2:1 between 3 MeV measurements and source development, over 3 weeks period or as best convenient. • DO NOT FORGET COMMISSIONING TIME FOR DIAGNOSTICS BCC 41 - 3MeV test stand measurements

  12. Proposal - • 3 MeV beam commissioning must be done in 2 sessions/day on the basis 5 days/week . E.g. 7:00- 14:00 and 14-21 • We (BD team) are 3 staff + 3 visitors • Daily brief meeting with the people on the field + 1 by-weekly meeting in the control room to take decisions – CALLED BY GB • Need experts available as much as possible (in 2011 we “took it easy” but it took 6 months to measure the LEBT!) BCC 41 - 3MeV test stand measurements

  13. Something has to give… • Laser stripping measurements ( make sure that BI is made aware) • Halo measurements under different matching • Matching to the DTL • Buncher optimisation • Pencil beam scans • Calibration of TOF vs. spectrometre…….. And many more The time presently allocated for commissioning in the tunnel is not sufficient-need 6 months We should repeat the measurements after the RFQ in the tunnel BCC 41 - 3MeV test stand measurements

More Related