1 / 4

Mock-up activities

Mock-up activities . 19 July 2011 R. Vuillermet. Mock up activities. Status 12-07-2011 :Reception of the pit table at CERN Since a week, installation of the optical fibbers on the mock up, side A done, side C on progress

lucian
Télécharger la présentation

Mock-up activities

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mock-up activities 19 July 2011 R. Vuillermet

  2. Mock up activities • Status • 12-07-2011 :Reception of the pit table at CERN • Since a week, installation of the optical fibbers on the mock up, side A done, side C on progress • Installation and adjustment of the pit table on the rotating table during the week 29 • Installation of the wire tension system during week 29

  3. LPSC Tooling fabrication progress Pit table delivered to CERN Thin tables and container (delivery week31/32) Pit table assemble with thin table Intermediate table assembly (delivery week30)

  4. Test schedule

More Related