An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PACIFIC PARTNERSHIP 2012 25 JAN 12 OPT Brief This brief is classified: UNCLASSIFIED

  2. Roll Call CDS-7 State Dept – Mr. Weinz USNS MERCY AUS HQ JOC HQ JFNZ JSDF FLC-Yokosuka C7F • C3F • CTF 76 • 351st Civil Affairs Command • DLA Troop Support - Pacific • ETG • 30th NCR • HSC-21 DET 2 • MCAST Blue: Normal participants not expected to attend VTC due to scheduling conflict.

  3. PP 12 Weekly Planning Rhythm 1100W read ahead slides posted to APAN CPF N3 Semi-Monthly Update 1200W MED WG Sun Mon Tues Wed Thurs Fri Sat 1300-1500W OPT VTC 1430W Comm Integration WG 1000W COMMS WG 1000W CA WG 1300W LOG WG 1200W ENG WG 1300W FP WG Every other week Effective 09 JAN

  4. Planning Timeline PLANORD EXORD Mid Planning Conference Initial Planning Conference CPF RFF FSLO Letter MOU Letters Signed PN Invitation letters Final Initial Requirements Systems Assessment plan Advanced Echelon PDSS Deployment

  5. ADF Planning Status General Planning CJOPS Decision Brief for PP12 signed. Command Nomination of O-5 for position of COMASC submitted. Call for nominations for ASNCE staff sent via signal. Engineering Two (2) ADF engineers participated in Indonesia PDSS. Still awaiting Post Activity Report. Authorization to lead as FIE for Indonesia mission still to come from IPDIV. Medical Awaiting nominations for ADF Health PP12 positions from Services. No Change

  6. ADF Participation Australia Command Element Engineering Section Medical Personnel contribution of 15 – 20 pers in each contingent Contingent 1 embark USNS MERCY in Guam and change out in Subic Bay Philippines Contingent 2: embark USNS MERCY in Subic Bay Philippines and disembark at the conclusion of mission in Cambodia Health manning TBC in late November HQJOC Health PP12 POC: CMDR Kenneth Walters (SO1 Reg / Dom & Joint Ex Hlth Plans) kenneth.walters@defence.gov.au No Change

  7. PP12 RFI Tracker No Change

  8. JSDF Planning Status • CONOPS of Japan - Developing the CONOPS of Japan Country selection - Philippine - Vietnam Activities - Medical supports - Community service projects Introduction of culture etc. - Studying other activities - Decision after completion of PDSS Vehicles - JMSDF Ship (TBD×1) - JASDF Aircraft(C-130orKC-767×1) Medical team - Approximately 20~30 No Change

  9. JSDF Planning Status • PDSS • -Request re-survey Philippines with U.S. survey team in FEB or MAR • 2012 • Humanitarian community in Japan • - Not yet access • POC • PRI: LCDR Haga : j3haga@jso.mod.go.jp DSN:224-7714 or 7723 • SEC: LCDR Yamaguchi : j3yamaguchi_m@jso.mod.go.jp No Change

  10. JSDF Planning Status No Change

  11. NZDF Planning Status • Decision by COMD Joint Forces New Zealand is to deploy a small multi-disciplinary health team for the duration of the deployment to Vietnam 10 – 24 Jul 12. • Contingent: Plan to embark USNS MERCY in Subic Bay Philippines / disembark at the conclusion of mission in Vietnam. • MAJ BROOKS – will attend Main Planning Conference (30 - 31 Jan in San Diego) • as HQ JFNZ Rep. Now registered into APAN, awaiting membership to PP12 accounts. • Medical Personnel contribution: Manning TBC in early December (8 – 12 pers) • New HQJFNZ Health PP12 POC: MAJ Andrew BROOKS • DDI: +64 4 529 6124 • andrew.brooks@nzdf.mil.nz No Change

  12. CPF FOPS Update • Manning Update • FFC change in sourcing priorities • Augmentation package was due back from Joint Sourcing on 23 Jan • Army input still outstanding, needed for 351st(16 pax) and 807th(25 pax) support • FFC Staffing not submitted • Commitment received for med personnel • CPF PLANORD released

  13. Medical Update • Medical WG Telcon held Tuesday, 24 January 2012, 1200 hrs • LT JG Ward to attend MPC and stay to assist with Medical CONOPS development • Funding provided by CPF and MERCY • Medical assessment to Philippines is GTG • Per ODC during 1/24 telcon, medical assessment to Cambodia rescheduled • 26 March – 3 April

  14. Engineering Update Site Survey Projects Recommended SMEE Request Philippines 3 schools & 1 medical clinic Seawall-Dr. Lin Cambodia 3 health centers Bldg; P&E; CCAD Indonesia 3 health centers & 1 school Seismic; Disaster Vietnam 2 health centers Disaster; Safety Australian Defence Force approval is approximately 90% complete. -ADF determination of FIE will follow site survey report Philippine Project Package preparation (ACB1 lead- BUC Sarmiento) Cambodia Project Package preparation (NMCB40 lead) Indonesia Project Package preparation (ADF lead/NMCB40 Alt) Vietnam Project Package preparation (NMCB40 lead) On-track Off-Track/Recoverable Off-Track not recoverable Completed

  15. Engineering Update Indonesia SMEEs: • Seismic Construction Practices • Disaster Response Plans Philippine SMEEs: • Project planning training using Microsoft Projects software • Repair and/or reconstruction of seawalls Vietnam SMEEs: • Construction Safety Practices • Engineer Disaster Response Plans Cambodia SMEEs: • Building Plan Development • Water Quality On-track Off-Track/Recoverable Off-Track not recoverable Completed

  16. Logistics Update • Logistics WG held 24 Jan 12 • Reviewing proposed Medical CONOPS to develop logistics support plan(s) • Funding • APRI (No Change) • MTF MERCY received $600K of required $1.9M • Pharmaceuticals and Consumables • Working with DLA to assign Call Numbers for initial orders • Donation Material (No Change) • Next Logistics WG meeting scheduled for 7 Feb 12

  17. PP12Supply and Logistics StatusFUNDING (25 JAN12) NO CHANGE 17 Completed On-track Off-Track/Recoverable Off-Track not recoverable

  18. PP12 Supply and Logistics StatusPHARMACEUTICALS and CONSUMABLES (25JAN12) 18 On-track Off-Track/Recoverable Off-Track not recoverable Completed

  19. PP12 Supply and Logistics StatusDONATION MATERIAL (25JAN12) 19 NO CHANGE On-track Off-Track/Recoverable Off-Track not recoverable Completed

  20. PP12CIS Information Systems Status(25JAN12) 20 No Change On-track Off-Track/Recoverable Off-Track not recoverable Completed

  21. PP12CIS Information Systems Status(25JAN12) 21 On-track Off-Track/Recoverable Off-Track not recoverable Completed

  22. PP12CIS Information Systems Status(25JAN12) 22 On-track Off-Track/Recoverable Off-Track not recoverable Completed

  23. PP12CIS Information Systems Status (25JAN12) 23 No Change On-track Off-Track/Recoverable Off-Track not recoverable Completed

  24. PP12CIS Information Systems Status(25JAN12) 24 On-track Off-Track/Recoverable Off-Track not recoverable Completed

  25. Force Protection Update • MFP Sourcing: Four Marines, possibly participation at MPC • C7F/CTF-76 tasking to re-analyze manning needs • PIVA update • MPC coordination • Pre-Deployment travel Requirements • Updated ISOPREPs • APACS • iATP • AOR location specific brief • Level I ATFP • SERE 100 B

  26. Public Affairs Update • Admin • Mission PAO to DC 15-18 JAN for CHINFO/OSD/DOS meetings/coordination for mission roll-out • Media Coordination • CAPT Breslau, LCDR Lohmeyer will meet with Warner Bros. and NAVINFO WEST in LA 25 JAN

  27. Public Affairs Update On-track Off-Track/Recoverable Off-Track not recoverable Completed

  28. Public Affairs Update On-track Off-Track/Recoverable Off-Track not recoverable Completed

  29. CAWG Update (25 JAN)

  30. Projected Host and Partner Nation Participation by Port

  31. UNCLASSIFIED Projected NGO Participation by Port UNCLASSIFIED

  32. UNCLASSIFIED Projected NGO Participation by Port UNCLASSIFIED

  33. PP12 APRI/OHDACA Status: 17JAN11 APRI Summary OHDACA Summary

  34. Canadian Team • Two CA Teams • Team One: HS support to Indonesia and Philippians • Duration - 8 May to 3 Jul 12 • Embark - PEARL HARBOR 9 May 12 • Disembark - SUBIC BAY 4 Jul 12 • Team Two: HS support to Vietnam and Cambodia • Duration – 3 Jul to 4 Sep 12 • Embark – SUBIC BAY 4 Jul 12 • Disembark – PEARL HARBOR 4 Sep 12

  35. Canada: HSS TO&E *Focus – Primary Care*

  36. PP12 Communication Integration Finalizing products to support detailed communication planning and assessment for each location (due 30 JAN) Coordinating communication assessment support for PP12 (MAY – SEP 12) Include “baseline” and post-mission support Linguist support Next CIWG meeting scheduled for: 26 JAN 12 AMEMB Cambodia, Vietnam Telecons being coordinated

  37. PP12 Communication Integration Completed 37 Off-Track not recoverable On-track Off-Track/Recoverable

  38. PP12 Communication Integration 38 Completed On-track Off-Track/Recoverable Off-Track not recoverable

  39. Planning Timeline INDICATES UPDATE UPDATED: 18JAN12

  40. Mission Commander Priorities Country CONOPS Development 30-Jan-12 MPC (PRESENT DRAFT CONOPS) Mid Planning Conference (29-31JAN) 29JAN Civilian Participant Planning and Discussion (USNS MERCY) 30-31JAN MPC Agenda (next slide) (ADMIRAL KIDD CONF CENTER) CMCC TTX (01FEB12) Notification/agenda/objectives provided; participants confirm via RSVP SLV preparations Big-block travel arrangements made Issues: CPF participant requested Vietnam Visas (What is the backup plan?) Agenda / KLE Miscellaneous Manning / billet gaps (lacks a clear path to resolution) Landside FP sourcing (lacks a clear path to resolution) Proposed Mission Planning Rhythm in development CMCC Watchfloor products in development: SORM / SOPs / Watchbills / PPRs

  41. PP12 MPC Agenda 30JAN12 • 0700-0800 REGISTRATION • 0800-0805 PP12 MISSION COMMANDER OPENING REMARKS (CDS7 N00) • 0805-0815 ADMIN REMARKS (CDS7 N3) • 0815-0900 CONOPS - INDONESIA (CDS7 PDSS/ADVON GOLD OIC) • 0900-0910 BREAK • 0910-0955 CONOPS - PHILIPPINES (CDS7 PDSS/ADVON BLUE OIC) • 0955-1005 BREAK • 1005-1050 CONOPS - VIETNAM (CDS7 PDSS/ADVON GOLD OIC) • 1050-1100 BREAK • 1100-1145 CONOPS - CAMBODIA (CDS7 PDSS/ADVON BLUE OIC) • 1145-1300 MPC GROUP PHOTO / LUNCH BREAK • 1300-1600 FUNCTIONAL WORKING GROUPS • 1600-1630 WRAP UP MEETING / WAY AHEAD FOR 31JAN (WORKING GROUP LEADS, PDSS/ADVON OIC/AOIC, COORDINATORS) • 1800-2000 SOCIAL (SAMMY'S WOODFIRED PIZZA, POINT LOMA/LIBERTY STATION) 31JAN12 • 0730-0745 ADMIN REMARKS (CDS7 N3) • 0745-1200 FUNCTIONAL WORKING GROUPS (CONT) • 1200-1300 LUNCH • 1300-1530 FUNCTIONAL WORKING GROUPS (CONT) • 1530-1550 DELIVERABLES / WRAP-UP (CDS7 N3) • 1550-1600 PP12 MISSION COMMANDER CLOSING REMARKS (CDS7 N00)

  42. Closing Questions/Comments CPF Staff State Dept – Mr. Weinz AUS HQ JOC HQ JFNZ JSDF FLC-Yokosuka C7F C3F CTF 76 • 351st Civil Affairs Command • DLA Troop Support - Pacific • 30th NCR • ETG • HSC-21 DET 2 • MCAST • USNS MERCY • CDS-7