Drought Impacts

Drought Impacts. Power Production for Boulder Canyon Project & Parker-Davis Project. Impacts To Date. Future Drought Impacts Boulder Canyon Project. How Is Hoover Generation Impacted If Drought Continues?. Reduced Head as Lake Mead Storage Decreases

tieve
Télécharger la présentation

Drought Impacts

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Drought Impacts Power Production for Boulder Canyon Project & Parker-Davis Project

  2. Impacts To Date

  3. Future Drought Impacts Boulder Canyon Project

  4. How Is Hoover Generation Impacted If Drought Continues? • Reduced Head as Lake Mead Storage Decreases • Lake Mead Level Drops 10-15 ft. per year with min. objective release (8.23 MAF) from Powell • Reduced Water Releases When Shortages are Implemented • No Physical Restrictions But Turbine Output Decreases With Lower Elevation & Water Releases

  5. Hoover Key Elevations

  6. Turbine Operation • Design Head for Turbine Equates to About 1160 ft. Elevation • Turbines Probably Able to Operate Below 1050 ft. (Minimum Power Pool) at Greatly Reduced Output • Increased Cavitation & Maintenance at Lower Elevations. More Operational Limitations.

  7. How Far Can Lake Mead Elevation Drop? • Shortage Protection Criteria Determine the Elevation(s) at Which Water Deliveries are Reduced • No Shortage Protection Criteria Adopted by Reclamation - Basin States Discussing Alternatives • Absolute Floor Probably 1000 ft. (Nevada Intakes)

  8. Mitigation Measures • Turbine Replacements • Stainless Steel Wicket Gates • Involvement In Shortage Protection Criteria/Basin States Discussions • Operation of Desalter or Other Bypass Alternatives & Reducing Over-Deliveries to Mexico

  9. Turbine Replacements • Increased Capacity (10-15%) • Small Increase In Efficiency & Energy • Reduced O&M Costs/Operational Limitations • Cost Approximately $1.3M per Turbine • Cost Effectiveness • Quick Payback at Lower Elevations • USBR Doing Preliminary Evaluation • Replacements Done in Increments

  10. Stainless Steel Wicket Gates • Increased Capacity (5%) • Small Increase In Efficiency & Energy • Reduced O&M Costs • Cost Approximately $1.0M per Turbine • Cost Effectiveness • Quick Payback; Not Dependent Upon Elevation • USBR Doing Preliminary Evaluation • Replacements Done in Increments

  11. Shortage Protection Criteria • Shortage Protection at Higher Elevations Equates to Higher Capacity & Energy • Same Amounts of Water is Delivered in Long Run • Storage Between 1000’ & 1050’ = 3 MAF

  12. 1100 ft. vs. 1050 ft. Avg Capacity = 1573 MW vs 1409 MW (11.6% Diff) Avg Energy = 3392 GWH vs 3174 MW (6.9% Diff) Same Total Water Deliveries

  13. Other Measures • Reducing Bypass Flows to Mexico (Desalter or Fallowing) • Additional Storage in Yuma Area Would Reduce Over-Deliveries to Mexico • Combined Maximum Reduction in Releases Would be 200 KAF or Less

  14. Future Impacts Parker-Davis Project

  15. Impacts on Parker-Davis Generation • No Change in Lake Mohave & Lake Havasu Target Elevations • Therefore Head is Not Affected at Parker & Davis Dams and Generation Varies Only With Water Releases • Lake Mead Elevation Below 1125 ft. Results in Normal Water Year Releases • In Normal Water Years P-D Generates About Current Contract Levels of 1346 GWh (Slightly Less Than FY03)

  16. Impacts on Parker-Davis Generation(Cont.) • In Shortage Years Davis Generation Is Reduced Almost Proportionally to Water Reductions • Parker Generation Should Be Unaffected Since Most or All Reductions are Above Parker • Davis Generation About 80%, Parker Generation About 20 % of Parker-Davis Generation • Example: 10% Reduction In Water Deliveries = 8% Reduction In Parker-Davis Generation

  17. Probable Future Hoover & Parker-Davis Generation

  18. Recent Generation Studies Boulder Canyon Project Through 2017 • Average Capacity = 1637 MW • Average Energy = 3889 MWh (No Modifications to Units)

  19. Recent Generation Studies Parker-Davis Generation Through 2028 • Average Energy = Approx. 1380 GWh (Reviewing Numbers)

  20. Mead Filling • Requires Average or Greater Colorado River Basin Runoff • Lake Powell Fills First Until Volume Greater Than Lake Mead (Equalization) • Possible to Completely Refill in Few Years But Requires Very Unusual Runoff (Similar to Early 80’s)

  21. Probable Future GenerationSummary • BCP Generation Between 3600 GWh and 4100 GWh Most Years • P-D Generation Near Current Contract Energy of 1346 GWh Most Years • Lake Mead Must Fill Above Elevation 1145 ft. for Generation Significantly Above These Values • Generation Would be Significantly Below These Values Only in Water Shortage Years

  22. For Additional Information Contact: Brian Young byoung@wapa.gov or 602-352-2594