SlideServe
Menu
Préférences
© SlideServe · v2026

Preliminary Results of TI2 Collimator Beam Commissioning - LHC Working Group Meeting, 2008

treva avatar
10 diapositives · 243 Views · Sep 23, 2014

The LHC Collimator Working Group held a meeting in Geneva on June 16, 2008, to discuss the preliminary results of TI2 collimator beam commissioning. Key participants, including O. Aberle and R. Assmann, presented findings from tests involving three TCDI collimators under various beam conditions. Successful collimator setups were achieved, showing stable beam intensity with variations of only 10-20%. Scans conducted on the collimators provided significant data on beam losses and transmission efficiency. Initial analytics indicated a good agreement with independent beam emittance measurements.

Preliminary Results of TI2 Collimator Beam Commissioning - LHC Working Group Meeting, 2008 - slide 1
01 / 10Preliminary Results of TI2 Collimator Beam Commissioning - LHC Working Group Meeting, 2008
1 / 17

Télécharger la présentation

Preliminary Results of TI2 Collimator Beam Commissioning - LHC Working Group Meeting, 2008
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. LHC Collimator Working Group meeting Geneva, 16th June 2008 Preliminary results of TI2 collimator beam commissioning • O. Aberle, R. Assmann, M. Brugger, V. Kain, A. Masi, V. Previtali, S. Redaelli, T. Weiler, J. Uythoven ... • Special thanks to R. Giachino

  2. Hardware involved Beam commissioning of THREE TCDI collimators in TI2 Beam conditions: single and multi-bunches, ~5x1010p per bunch

  3. Collimator tests Beam availability - extracted intensity Very good conditions for collimator set-up studies: stable orbit an optics. Extracted beam intensity stable to 10-20%

  4. Beam-based set-up Basic idea: scan jaw through the beam and measure beam losses / intensity transmission. Preliminary results in good agreement with independent measurements of beam emittance (using nominal optics). Analysis of beam intensity data (transmission / scale BLM reading) to be done. Example: scans with LEFT and RIGHT for the TCDIV-29012 (σy ≈ 300 μm)

  5. Beam-based set-up Basic idea: scan jaw through the beam and measure beam losses / intensity transmission. Scan by moving the center of the jaws. Aperture= 1mm. (data not yet normalized with intensity) Example: scans by moving the center of the jaws TCDIH-20607 (σx ≈ 650 μm)

  6. Collimator in “protect” settings Collimator set at 4.5 sigma around the beam orbit (beam-based values used) V. Kain

  7. LVDT noise reduction 2007: TI2 pulsing, no beam 80 μm 2008: TI2 pulsing, with beam 10 μm

  8. Still one bad guy... LVDT Right-Downstream of TCDIH-29050 Shielding will be optimized as soon as access is available

  9. LVDT noise induced by the beam (I) Drift of the LVDT read-out value when the beam impacted on the collimator jaw. Signal goes back to the correct value if we switch the beam off. Problem disappeared by itself after one hour

  10. Collimator Logging 1246 logging variables set-up for 7 collimators in TI2 (test-bench for the complete system). Still need to check them all systematically, but the first feedback is very positive! Temperature logging not yet configured. Thanks: R. Billen, C. Roderick, N. Hoibian, M.Gourber-Pace