Vacuum Components Undulator System

Vacuum Components Undulator System. SH Lee, J Morgan, and D Walters. Major Components. Vacuum Chamber Support Bellows Quadrupole Spool BFW Support RFBPM Support Long Break Spool Chambers Girder Extensions. Vacuum Chamber Support. Vacuum Chamber Support. Adjustment Mechanism.

frigsby
Télécharger la présentation

Vacuum Components Undulator System

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Vacuum ComponentsUndulator System SH Lee, J Morgan, and D Walters

  2. Major Components • Vacuum Chamber Support • Bellows • Quadrupole Spool • BFW Support • RFBPM Support • Long Break Spool Chambers • Girder Extensions

  3. Vacuum Chamber Support

  4. Vacuum Chamber Support

  5. Adjustment Mechanism

  6. Vacuum Chamber Support • Tubular Chamber Support • First Article shipped from ANL 1/13/08, expect arrival at SLAC on 1/23/08 • Expect balance to ship 2/16/08 • Adjustment Mechanism • Expect First Article to ship1/24/08 • Expect final group 1 (35) to ship 2/22/08

  7. Bellows

  8. Bellows • E7-345050 Flange and Bellows Assy. • Award No:         8A-03419            • Award Date:       01/11/2008 • Supplier:         APPLIED ENERGY SYSTEMS INC                                                      • Delivery Date: 05/11/2008 Based on the vendor's delivery schedule in the quote, It is expected on 02/16 for 1st article and completion 03/16 • E7-352011 for Beam Tube • Award No:         8A-03623            • Award Date:       01/16/2008 • Supplier:         WALCO TOOL & ENGINEERING CORP  • Delivery Date: 03/16/2008 It is expected on 02/16 for 1st article and completion 03/16 • Cleaning, baking, and assemble at the APS before sending to SLAC • Best estimate for the completed units 2/25/08 for the First Articles and the balance by 3/25/08

  9. Quadrupole Spools • First Articles are at ANL Aluminum was plated onto parts

  10. Quadrupole Spools Best estimate of shipping (3) First Articles is 1/28/08 Balance to ship 2/21/08

  11. BFW & RFBPM Support • BFW Support • First Article planned to ship on 1/24/08

  12. Long Break Chambers • The requisition for this has just recently been written. Seeking delivery of this to be 8 weeks. • Chambers will have to come to ANL for leak check, clean, and bake.

  13. Girder Extension • The requisition for this has just recently been written. Seeking delivery of this to be 8 weeks.