E-Tag Issues Work Group Report 8/15/12. Lisa Wildes Gila River Power LLC. E-Tag Issue. Source BA denying curtailments done 10 mins in the past Have their system set for 5 mins Feel following INT-010-WECC-CRT-2 violates NAESB standards in regards to inadvertent and reliability timelines
E N D
E-Tag Issues Work Group Report8/15/12 Lisa Wildes Gila River Power LLC
E-Tag Issue • Source BA denying curtailments done 10 mins in the past • Have their system set for 5 mins • Feel following INT-010-WECC-CRT-2 violates NAESB standards in regards to inadvertent and reliability timelines • They previously brought these issues to the OC but were “ignored” • EIWG recommended that they follow the 10-min rule and submit comments on WECC-0077, which was out for comment at the time
Proposed Guideline for e-Tag Ramp Durations • At April 2012 meeting, ISAS voted to put the proposed guideline out for comment • May 4 – Posted for 30-day comment period • June 26 – EIWG discussed comments via webinar • June 27 – Comments and revised guideline posted for ISAS review • June 29 – WECC notified ISAS that approval items had been posted
Proposed Guideline for e-Tag Ramp Durations • Comments received from the CAISO and Powerex • Compressed tables into one by deleting all of the request types since the ramp durations were the same for all • Added a column in for curtailments since there were exceptions for this specific request type
Proposed Guideline for e-Tag Ramp Durations • Right after posting the revised guideline, this was brought to my attention: INT-011-WECC-CRT-2, Ten Minute Recallable Reserves, posted at http://www.wecc.biz/Standards/Development/WECC-0079/default.aspx states: WR2. Each Purchasing-Selling Entity and each Source Balancing Authority that activates recallable reserves shall submit a downward e-Tag adjustment that includes each of the following characteristics: 1) A start time that is no earlier than ten minutes prior to the submittal time. 2) A default ramp duration of zero. Fix: change default ramp duration in table to 0?
Proposed Guideline for e-Tag Ramp Durations • MOTION: Approve (amended) Guideline for e-Tag Default Ramp Durations