1 / 39

Steady-State Cascading Failure Analysis in TransCARE Models and Application

Steady-State Cascading Failure Analysis in TransCARE Models and Application. Murali Kumbale Southern Company Services Inc. Bulk Transmission System Reliability Atlanta, GA 30308. Highlights of TransCARE of Cascading Failure Analysis. TRELSS has now been superseded by TransCARE

norman
Télécharger la présentation

Steady-State Cascading Failure Analysis in TransCARE Models and Application

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Steady-State Cascading Failure Analysis in TransCAREModels and Application MuraliKumbaleSouthern Company Services Inc.Bulk Transmission System ReliabilityAtlanta, GA 30308

  2. Highlights of TransCAREof Cascading Failure Analysis • TRELSS has now been superseded by TransCARE • Cascading failure analysis in TransCARE is currently confined to system response in steady-state. • Cascading failure analysis requires determination of protection and control groups based on breaker locations. • WECC system breaker locations were unavailable for the CIEE project • Automatic breaker placement in TransCARE was utilized to superimpose breaker locations upon the supplied power flow model.

  3. Highlights of TransCAREof Cascading Failure Analysis • Based upon breaker locations TransCAREidentifies what is termed as Protection and Control Groups (PCG) • PCGs roughly correspond with the primary zone of protection. • Simulation of breaker actions provides a more realistic foundation for performing cascading failure analysis

  4. Sample Protection and Control Group (PCG)

  5. First Initiating Event Start Continue solution Solve Power Flow During the solution Bus Voltages < “Voltage Collapse” Threshold? Load Bus Voltages < Threshold? No Yes Disconnect Loads No Yes Drop Load @ Affected Buses Generator Bus Voltages < Threshold? Yes Trip Generators No Largest Circuit Overload > Threshold? Trip PCG Containing Circuit Yes SimulationApproachFlowchart No No Yes Next Initiating Event Last Initiating Event? Stop

  6. First Initiating Event Start Solve Power Flow SimulationApproachFlowchart

  7. First Initiating Event Start Solve Power Flow During the solution Bus Voltages < “Voltage Collapse” Threshold? SimulationApproachFlowchart

  8. First Initiating Event Start Continue solution Solve Power Flow During the solution Bus Voltages < “Voltage Collapse” Threshold? No Yes Drop Load @ Affected Buses SimulationApproachFlowchart

  9. First Initiating Event Start Continue solution Solve Power Flow During the solution Bus Voltages < “Voltage Collapse” Threshold? Load Bus Voltages < Threshold? No Yes Drop Load @ Affected Buses SimulationApproachFlowchart

  10. First Initiating Event Start Continue solution Solve Power Flow During the solution Bus Voltages < “Voltage Collapse” Threshold? Load Bus Voltages < Threshold? No Yes Disconnect Loads Yes Drop Load @ Affected Buses SimulationApproachFlowchart

  11. First Initiating Event Start Continue solution Solve Power Flow During the solution Bus Voltages < “Voltage Collapse” Threshold? Load Bus Voltages < Threshold? No Yes Disconnect Loads No Yes Drop Load @ Affected Buses Generator Bus Voltages < Threshold? SimulationApproachFlowchart

  12. First Initiating Event Start Continue solution Solve Power Flow During the solution Bus Voltages < “Voltage Collapse” Threshold? Load Bus Voltages < Threshold? No Yes Disconnect Loads No Yes Drop Load @ Affected Buses Generator Bus Voltages < Threshold? Yes Trip Generators SimulationApproachFlowchart

  13. First Initiating Event Start Continue solution Solve Power Flow During the solution Bus Voltages < “Voltage Collapse” Threshold? Load Bus Voltages < Threshold? No Yes Disconnect Loads No Yes Drop Load @ Affected Buses Generator Bus Voltages < Threshold? Yes Trip Generators No Largest Circuit Overload > Threshold? Trip PCG Containing Circuit Yes SimulationApproachFlowchart

  14. First Initiating Event Start Continue solution Solve Power Flow During the solution Bus Voltages < “Voltage Collapse” Threshold? Load Bus Voltages < Threshold? No Yes Disconnect Loads No Yes Drop Load @ Affected Buses Generator Bus Voltages < Threshold? Yes Trip Generators No Largest Circuit Overload > Threshold? Trip PCG Containing Circuit Yes SimulationApproachFlowchart No No Yes Next Initiating Event Last Initiating Event? Stop

  15. Initiating Event Example Bus Tie Breaker Failure X

  16. Loaded > 125% Study Event Examples Voltage < 0.85% Bus Tie Breaker Failure X

  17. Study Event Examples Bus Tie Breaker Failure X

  18. Loaded > 125% Study Event Examples Bus Tie Breaker Failure X

  19. Study Event Examples Bus Tie Breaker Failure X

  20. Types of Extreme Events • NERC Reliability Standard types • Common right-of-way & common tower • Breaker failure • Bus-tie breaker failure • Bus differential (“all voltage level at a bus”) • All units at a plant • Infrastructure security types • Complete loss of a major plant or substation • Close-in common right-of-way • Simultaneous multiple transformer outages

  21. Why Analyze Extreme Events? • NERC Reliability Standard compliance • TPL-003 & TPL-004; extreme events that are not simple to simulate • Screening purposes • Identifies potential cascading or voltage collapse events for further study • Transmission project determination & prioritization • Determines projects to mitigate potential cascading failures

  22. Study Event Examples NERC Types

  23. Initiating Event Example Bus Tie Breaker Failure X

  24. X Initiating Event Example Common ROW or Tower

  25. X Initiating Event Example Common ROW or Tower

  26. Initiating Event Example X Breaker Failure - Ring Bus

  27. Initiating Event Example X Breaker Failure - Ring Bus

  28. Study Event Examples Bus Fault - Single Bus X

  29. Initiating Event Example Bus Fault - Single Bus X

  30. Other Severe Event Examples

  31. Other Severe Event ExamplesComplete Station Outage

  32. Other Severe Event ExamplesClose-in Right-of-Way Outage

  33. Other Severe Event ExamplesMultiple-Site Transformer Outages

  34. Post-9/11 Event ExamplesMultiple-Site Transformer Outages

  35. How The Results Are Used • Transmission project development, examples: • 230kV substation reconfiguration • Changed line terminations to prevent shared breakers between critical lines • 230kV bus differential • Changed to a ring bus • 230kV breaker failure • Installed another breaker and firewall • 230kV bus tie breaker failure • Installed a 2nd bus tie breaker • 115kV bus differential • Split the 115kV bus and installed a bus tie breaker

  36. How The Results Are Used • NERC Reliability Standard compliance • Determination of reliability impacts for possible non-compliances • “Critical Asset” determination • Process required by NERC Reliability Standards • Consider all study events that exceed 300 MW load loss • Input into Southern Company Security Council for development of mitigation & physical security plans • NERC Cyber Security Standards –“Critical Cyber Asset” determination

  37. Enhancing Cascading Failure Analysis Methodology

  38. Enhancing Cascading Failure Analysis Methodology

  39. Murali Kumbale Staff Engineer Bulk Transmission System Reliability Power Delivery/Transmission Southern Company Services, Inc. Bin 10050 241 Ralph McGill Blvd. Atlanta, Georgia 30308-3374 Tel 404.506.3715 Fax 404-506-2277 mkumbale@southernco.com

More Related