1 / 11

Big Stone II Study Update

Big Stone II Study Update. SPG Meeting October 19, 2006. Presentation Overview. Summary of September 18 MAPP DRS Mtg. Interconnection Study Delivery Service Study Phase 5 Summer Off-peak Analysis Model Assumptions Results Upcoming Schedule. Recap of Sept. 18 DRS Mtg.

seda
Télécharger la présentation

Big Stone II Study Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Big Stone II Study Update SPG Meeting October 19, 2006

  2. Presentation Overview • Summary of September 18 MAPP DRS Mtg. • Interconnection Study • Delivery Service Study • Phase 5 Summer Off-peak Analysis • Model Assumptions • Results • Upcoming Schedule

  3. Recap of Sept. 18 DRS Mtg. • Interconnection Study • Presentation given to MAPP DRS • Discussion led to conditional approval of the IC study with 4 follow-up items: • Verify ND Load Levels in Stability Models • Arrowhead-Weston 345 kV Stability Sensitivity • Resolution of local stability issues • Update DRS once transmission option selected by the MN PUC

  4. Recap of Sept. 18 DRS Mtg. • Delivery Service Study • Presentation given to MAPP DRS • Discussion led to identification of 4 follow-up items before DRS will take action on study. • Finish Phase 5 analysis (Summer off-peak study) • Prior outage analysis of Phase 3 models • Deeper explanation of flowgate analysis • Identify fixes for delivery related issues (revise motion)

  5. Phase 5 – Summer off-peak High Simultaneous transfer case • Phase 5 only for DRS review. Submitted to the DRS on Sept 29th for review at the November 2nd meeting • Not part of MISO submittals

  6. Technical Scope • This phase is steady state only • Base case is 2006 summer off-peak case from the NMORWG package with: • MHEX South = 2175 MW • NDEX = 1950 is base case – raised with Big Stone II • MWSI = 1480 MW prior to Arrowhead – Weston in service. Maintained at such level prior to Arrowhead – Weston throughout study. • Since this case has maxed out interfaces, the model does not reflect existing firm commitments. • Baseloads within NDEX @ URGE • Load within NDEX approx @ 70% • NMORWG TITLE: URG-S7006AA.UZVV424.SAV

  7. Powerflow model additions • Added some new topology: • Split Rock – Nobles Co. – Lakefield 345 kV • Lakefield – Fox Lake 161 kV #2 • Arrowhead – Stone Lake – Gardner Park 345 kV • Series Compensation of Lakefield – Wilmarth 345 kV • Upgrades associated with Council Bluffs 4 and Nebraska City 2 • Other miscellaneous model changes in addition to this

  8. Study • BSP II output sunk to generation similar to that of Phase 3 and 4 of the Delivery Study • One scenario for each of the two interconnection alternatives studied.

  9. Results • Thermal overloads observed, and impacted above 2% DF: • Big Stone – Blair 230 kV. Loaded between normal and emergency rating • Granite Falls 230/115 kV xmfrs • Aurora – Brookings 115 kV • Arlington – Watertown 115 kV • Brookings – Watertown 115 kV • McLeod 230/115 kV xfmr • Granite Falls – Morris 230 kV • Morris 230/115 kV xfmr • Watertown 345/230 kV xfmr • Johnson Jct. – Ortonville 115 kV • Grant County – Hoot Lake 115 kV

  10. Results - continued • Part of this study is to identify if TTC of interfaces would be reduced because of this project. Note that the model is not reflective of firm commitments. • Two of the thermal issues seen is part of the current NDEX interface definition: • Big Stone – Blair 230 kV • Morris – Granite Falls 230 kV • No new steady state voltage concerns observed. • Discussion on what the constraints that will have to be mitigated will be held at the DRS meeting.

  11. Upcoming Schedule • November 2 DRS Mtg. • Discuss Phase 5 Analysis • December 7 DRS Mtg. • Discuss Remaining Follow-Up Items • December 31 Draft IA • MISO Approval of IC Study • January 2007 Begin Phase 6 Analysis • Sensitivity to EHV line and other regional transmission projects

More Related