An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MUID FEE Status Vince Cianciolo Muon Meeting BNL, 12/16/2000

  2. The Pieces • FEMs • ROCs • Transition Cards • Passthrough Backplanes • Digital Backplanes • Crates • LV, HV Distribution boxes • Infrastructure

  3. South Status • FEMs - all parts in hand, boards being fabbed, will be in hand in January. • ROCs - First two tested. Assembly of next 13 started. Balance will wait until 3/1 for delivery of AMUX chip. • Transition cards - Boards and parts in hand. Will be assembled in early January.

  4. South Status, cont. • Passthrough backplanes - in hand. • Digital backplanes - should arrive before end of month. • Crates - first article at ORNL awaiting test. • Distribution boxes - in hand. • Infrastructure - in place. • Installation of cables and start of commissioning - pre-Quark Matter.

  5. North Status • FEMs, transition cards, backplanes, crates - ordered along with South. • ROCs - SOW submitted to order parts at ORNL. Could finish by August 2001 depending on long leadtime parts. • LV, HV boxes - No schedule yet. Can’t install before long shutdown, they will be done in plenty of time for that.

  6. North Status, cont. • Infrastructure - casually suggested by Tom Shea that we get this job done this shutdown - will push to get this done.