10 CFR 851 Worker Safety and Health Program Overview

10 CFR 851 Worker Safety and Health Program Overview. Worker Safety and Health Program 10 CFR 851. Brief History December 2, 2002 – 107 th Congress Amends AEA Adding Section 234.C December 18, 2003 - Notice of Proposed Rulemaking

Télécharger la présentation

10 CFR 851 Worker Safety and Health Program Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 10 CFR 851Worker Safety and Health ProgramOverview

  2. Worker Safety and Health Program 10 CFR 851 • Brief History • December 2, 2002 – 107th Congress Amends AEA Adding Section 234.C • December 18, 2003 - Notice of Proposed Rulemaking • February 27, 2004 - Notice Suspended • January 26, 2005 - Supplemental Notice Published • February 9, 2006 - Final Rule Published

  3. AEA - Section 234C • Secretary of Energy Shall Promulgate Regulations for Industrial and Construction Safety and Health • Provide a level of protection that is substantially equivalent to that currently provided. • Flexibility • Tailor to Reflect Activities and Hazards • Special Circumstances • National Security • Penalties • Civil Penalties up to $70,000 for each Violation, or • Contract Penalties

  4. Current Level of Protection • DOE Order 440.1A, “Worker Protection Management for DOE Federal and Contractor Employees” • Written safety and health program • Comply with worker protection standards • OSHA, NFPA, ANSI and ACGIH • Comply with requirements for functional areas • Construction safety, Fire protection, Firearms safety, Explosives safety, Industrial Hygiene, Occupational medicine, Pressure safety, and Motor vehicle • Non Mandatory Contract requirement • Negotiable (‘B’ List)

  5. 10 CFR 851- General Provisions • Scope • Contractor activities at DOE • Exclusions • Sites Regulated by OSHA • Navy Nuclear Propulsion • Radiological Hazards (10 CFR 835) • Transportation To and From DOE sites

  6. General Duty • General Duty • Provide a place of employment free from recognized hazards that have the potential to cause death or serious physical harm • Work is Performed in Accordance with Worker Safety and Health Program

  7. Worker S&H Program Requirements - I • Written Safety and Health Program • Approved by Head of DOE Field Element • Submitted by February 26, 2007 • Copy Sent to Chief Health, Safety and Security Officer • Give Labor Organization Timely Notice • Must be Approved by May 25, 2007

  8. Worker S&H Program Requirements - II • Written Safety and Health Program • Describe How Contractor Will Comply with Requirements of Subpart C • May Use ISM or WSS as the basis for their WS&H Program • Integrate Requirements with other Site Worker Protection Activities • Integrate with ISMS • No Work if NOT Approved by May 25, 2007

  9. Subpart C Program Requirements Overview - I • Management and Worker Responsibilities • Same as DOE O 440.1A • Hazard Identification • Assess Exposures to Chemical, Physical, Biological and Safety Hazards • Closure Facility Hazards and Controls • Hazard Prevention • Hierarchy of Controls • Safety and Health Standards • 29 CFR, ANSI, NFPA, ASME

  10. Subpart C Program Requirements Overview - II • Functional Areas (Appendix A) • Construction, Fire Protection, Explosives, Pressure, Firearms, Industrial Hygiene, Biological, Occupational Med, Motor Vehicle • Training • Train Workers and S&H Staff • Record Keeping • DOE M 231.1-1A • References • Lists Required Standards

  11. Variances • Similar to OSHA • Application – Approval Process • Contractor Cog. Sec. Officer HSS review Under Sec/Administrator Approval • Variance Types • Temporary • Permanent • National Security • Electronic Variance Application Process • Available on line

  12. Implementation Assistance • Meetings with Tele-video • Federal DOE HQ and Field staff • Workshops • Federal and Contractor Attendance • 10 CFR 851 Web Site • http://www.hss.energy.gov/HealthSafety/WSHP/rule851/851final.html • Implementation Guide (DOE G440.1-8) • Response Line for Questions • 800-292-8061 or 301-903-9976