A detailed summary of the successful maintenance and support work during RHIC Run 10 on May 19th, including executing over 100 individual jobs, effective work scheduling, excellent contributions from Vacuum and Instrumentation Groups, and quick restoration of physics operations. The schedule for the day and upcoming tasks are outlined for clarity.
E N D
Maintenance and Accelerator Support RHIC run10
Results May 19th: • A long day, well executed • 100+ individual jobs executed • Work Scheduling and planning was successful, both prior and during the day. • Excellent work, especially Vacuum and Instrumentation Groups. • Physics restored by 9pm-not bad. • I limit key is in the control room!
Thursday: • No Injector Access • Tandem down for 3 hours to change foil holder position • RHIC RCA access for: • PHENIX (ring and tunnel) • RHIC PSG (8Z2, 9Z1) • Sectors 5-9 for HP survey • NSRL running protons all day • Some “transparent” ACS work at Booster- back out plan of problems
Draft Schedule: • 0800: • 7.7GeV run ends • Begin RCA Access to IRs • HP surveys, RAC 3 groups • 0900: • Access 9Z1 for inspection with HP on RCA • 1000: Begin setup for 11.5 GeV running