1 / 50

Hydrologic Design and Design Storms

04/18/2005. Hydrologic Design and Design Storms. Readings: Applied Hydrology Sections 13.1-13.2.

callie
Télécharger la présentation

Hydrologic Design and Design Storms

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 04/18/2005 Hydrologic Design and Design Storms Readings: Applied Hydrology Sections 13.1-13.2

  2. Hydrologic extremes • Extreme events • Floods • Droughts • Magnitude of extreme events is related to their frequency of occurrence • The objective of frequency analysis is to relate the magnitude of events to their frequency of occurrence through probability distribution • It is assumed the events (data) are independent and come from identical distribution

  3. Hydrologic design • Water control • Peak flows, erosion, pollution, etc. • Water management • Domestic and industrial use, irrigation, instream flows, etc • Tasks • Determine design inflow • Route the design inflow • Find the output • check if it is sufficient to meet the demands (for management) • Check if the outflow is at safe level (for control)

  4. Hydrologic design scale • Hydrologic design scale – range in magnitude of the design variable within which a value must be selected • Design considerations • Safety • Cost • Do not design small structures for large peak values (not cost effective) • Do not design large structures for small peak values (unsafe) • Balance between safety and cost.

  5. Estimated Limiting Value (ELV) • Lower limit on design value – 0 • Upper limit on design value – ELV • ELV – largest magnitude possible for a hydrologic event at a given location, based on the best available hydrologic information. • Length of record • Reliability of information • Accuracy of analysis • Probable Maximum Precipitation (PMP) / Probable Maximum Flood (PMF)

  6. TxDOT Recommendations

  7. Hydrologic design level • Hydrologic design level – magnitude of the hydrologic event to be considered for the design or a structure or project. • Three approaches for determining design level • Empirical/probabilistic • Risk analysis • Hydroeconomic analysis

  8. Empirical/Probabilitic • P(most extreme event of last N years will be exceeded once in next n years) • P(largest flood of last N years will be exceeded in n=N years) = 0.5 • Drought lasting m years is worst in N year record. What is the probability that a worse drought will occur in next n years? • # sequences of length m in N years = N-m+1 • # sequences of length m in n years = n-m+1

  9. Example 13.2.1 • If the critical drought of the record, as determined from 40 yrs of data, lasted 5 yrs, what is the chance that a more severe drought will occur during the next 20 yrs? • Solution: N = 40, m = 5 and n = 20

  10. Risk Analysis • Uncertainty in hydrology • Inherent - stochastic nature of hydrologic phenomena • Model – approximations in equations • Parameter – estimation of coefficients in equations • Consideration of Risk • Structure may fail if event exceeds T–year design magnitude • R = P(event occurs at least once in n years) • Natural inherent risk of failure

  11. Example 13.2.2 • Expected life of culvert = 10 yrs • Acceptable risk of 10 % for the culvert capacity • Find the design return period • What is the chance that the culvert designed for an event of 95 yr return period will not have its capacity exceeded for 50 yrs? The risk associated with failure of culvert when the flow exceed 95 yr flood in the next 95 years is: The chance that the capacity will not be exceeded during the next 50 yrs is 1-0.41 = 0.59

  12. Hydroeconomic Analysis • Probability distribution of hydrologic event and damage associated with its occurrence are known • As the design period increases, capital cost increases, but the cost associated with expected damages decreases. • In hydroeconomic analysis, find return period that has minimum total (capital + damage) cost.

  13. Beargrass Creek Case Study • Description of the Study Area • Hydrology & Hydraulics • Economic Analysis • Project Planning • Assessment of the Risk Based Analysis Methodology From “Risk Analysis and Uncertainty in Flood Damage Reduction Studies”, NRC Report: http://www.nap.edu/catalog.php?record_id=9971

  14. Beargrass Creek Study Area Ohio River North Fork Middle Fork South Fork 61 mi2 Drainage Area Buechel Br

  15. Levee on the Ohio River

  16. Pump Station at the Levee(Capacity 7800 cfs!)

  17. Concrete-Lined Channel

  18. Detention Pond Inlet Weir

  19. Beargrass Creek at the Detention Pond Pond OutletPipe

  20. Damage Reaches South Fork Beargrass Creek (12 miles) 1 15 14 13 Example Reach SF-9 12 11 2 10 Buechel Branch (2.2 miles) 5 9 3 4 7 6 4 8 3 2 5 1

  21. Beargrass Creek Case Study • Description of the Study Area • Hydrology & Hydraulics • Economic Analysis • Project Planning • Assessment of the Risk Based Analysis Methodology

  22. Flood Frequency Curve (SF-9)Separate curve for each reach and each plan

  23. Uncertainty in Frequency CurveReach SF-9, Without Plan Conditions

  24. Water Surface Profiles South Fork Beargrass Creek (202 cross-sects) 1 15 14 13 12 11 2 Buechel Branch (61 cross-sects) 10 5 9 3 4 7 6 4 8 3 2 5 1

  25. Water Surface Profiles

  26. Uncertainty in Stage-Discharge Constant Reduces prop. to depth SD= 0.5 ft at 100 yr flow

  27. Beargrass Creek Case Study • Description of the Study Area • Hydrology & Hydraulics • Economic Analysis • Project Planning • Assessment of the Risk Based Analysis Methodology

  28. Computation of Expected Annual Damage (EAD) Discharge (Q) Discharge (Q) Exceedance Probability (p) Stage (H) Damage (D) Damage (D) Stage (H) Exceedance Probability (p)

  29. Single-family residential Multi-family residential Commercial buildings Public buildings Automobiles Cemeteries Traffic disruption Utilities Damage Categories

  30. Structures p=0.002 p=0.01 p=0.1 p=0.999

  31. Each damage reach has an index location All structures are assumed to exist there First floor elevation adjusted to reflect the change in location within the reach Index Location p=0.01 Index for SF-9 p=0.1 p=0.5 Invert Rm 10.363 Rm 10.124 Rm 9.960

  32. h First Floor Elevation Building Damage • Value of the structure, V • Value of the contents, C = kV • k=V/C, contents to value ratio (~40%) • Damage is a function of depth of flooding, expressed as ratio,r(h), of value

  33. Value of structure, SD=10% of V for residential Commercial distribution described by Value of contents (SD of k in C=kV) Uncertainty in first floor elevation, SD=0.2ft Uncertainty in damage ratios, r(h) h First Floor Elevation Uncertainty in Building Damage

  34. Stage-Damage Curve Multi-family Residential, Reach SF-9

  35. Stage-Damage Curves • Each structure is treated individually • Stage-damage curve with uncertainty is produced for each damage category for each reach • Added together to give the total stage-damage curve for the reach(?)

  36. Beargrass Creek Case Study • Description of the Study Area • Hydrology & Hydraulics • Economic Analysis • Project Planning • Assessment of the Risk Based Analysis Methodology

  37. Planning Team • Three key people: • Planner: formulates project alternatives, works with local sponsor • Hydraulic Engineer: determines discharge and stage data • Economist: estimates damage, costs, benefits and does the risk analysis

  38. Planning Methodology • Identify potential project components (detention ponds, levees, …) • 22 initially proposed, 11 on Beargrass Creek, and 11 on Buechel Branch • Evaluate them all individually to see if net benefits are positive • 8 components on Buechel Branch eliminated • Combine components into plans, incrementally • 10 components in NED plan: 8 detention ponds, 1 floodwall, 1 channel improvement

  39. Three Plan Development Reaches 1 1 15 14 13 2 12 11 2 10 3 5 9 3 Buechel Branch 4 7 6 4 8 3 2 5 1

  40. Establish a target stage at each damage reach index point Find annual probability of exceeding that stage Find reliability of passing design floods Risk of Flooding Target Stage

  41. Assessment of Engineering Risk F(h) • Conditional probability • Assumes a particular flood severity • Annual probability • Integrates over all flood severities • Risk measures actually used • Annual exceedance probability • Conditional nonexceedance probability 1 Exceedance probability Nonexceedance probability 0 H Target Stage

  42. Annual exceedance probability Find pe for target stage at each Monte Carlo replicate Get expected value and median of pe values over all simulations Get long term risk as 1-(1-pe)n Computation of Engineering Risk Measuresfrom the Stage-Frequency Curve Q H H Q* Target Stage H* f1(Q|p) H* f2(H|Q) f3(H|p) p p Q pe p* p* Q* • Conditional nonexceedance probability • Find H* for given p* at each replicate • Find % of replicates for which H* < Target stage

  43. Beargrass Creek Case Study • Description of the Study Area • Hydrology & Hydraulics • Economic Analysis • Project Planning • Assessment of the Risk Based Analysis Methodology

  44. Overall Assessment • The core methodology is solid and is an advance in engineering practice of flood risk assessment • Focus is completely on damage reaches considered as statistically independent entities • Whole project risk and 25%,50%,75% damage values cannot be built up this way • Can specification of standard deviations of analysis variables be improved?

  45. Beargrass Creek 100 year Flood Plain Map MiddleFork South Fork

  46. Spatial Subdivision of the Region

  47. Whole Project Risk Assessment • Take a flood of severity, p, and integrate the damage along the reach • Without any plan (o) • With a plan (w) • Benefit of plan is B = Do - Dw • Randomize the flood discharge and stage for the whole project rather than for each reach • Compute project-based damage values for each randomization and use them to get B25, B75 values

More Related